RE2020 completion certificate: the compliance document that conditions acceptance and resale of the asset

The RE2020 completion certificate has become one of the first documents requested in the acquisition audit of a new asset, alongside the declaration of completion and conformity of the works (DAACT) and the certificate of non-challenge of conformity. Its absence, or a gap between the indicators declared at the planning permit stage and those recorded at completion, rarely leads to an immediate sanction: it leads to a price renegotiation, an additional condition precedent, a retention, or even a refusal of a bank drawdown. Since Ordinance No. 2022-1076 of 29 July 2022, which came into force on 1 January 2024, the document no longer certifies a mere taking into account of the rules but their compliance, which shifts the emphasis from formality to a commitment to conformity. This guide sets out who issues the certificate, at what point it fits into the completion chain, which categories of building have been covered since 1 May 2026, and what risk exposure the holder of the asset bears if the certificate is missing or a gap is found on a sale or refinancing.

What the RE2020 completion certificate attests exactly since 1 January 2024

Article L. 122-9 of the French Construction and Housing Code (CCH), in the wording resulting from Ordinance No. 2022-1076 of 29 July 2022 applicable since 1 January 2024, lays down the obligation:

"On completion of the construction works on buildings subject to a planning permit and of the renovation works on existing buildings subject to a planning permit, the client shall provide the authority that issued the authorisation with a document certifying compliance with the construction rules on energy and environmental performance provided for under Title VII of this book."

The previous wording, which referred to a document certifying that the rules had been "taken into account", has gone. Decree No. 2023-1175 of 12 December 2023 aligned the regulatory level: Article R. 122-24-3 CCH requires the client (maître d'ouvrage) to draw up a document certifying "that it has complied, or has had the project manager comply where the latter is responsible for a mission covering the design of the operation and the execution of the works" with the requirements of Articles R. 172-4 and R. 172-5.

The nuance is not a matter of drafting. A certificate of taking into account read as a statement of method. A certificate of compliance reads as a statement of result, enforceable against the client by the authorities during the period of the right of inspection, and by a purchaser in contractual discussions. That is precisely what makes it a liquidity document: it records in writing, at the completion date, the performance level of the asset.

The exact scope of the certificate

Article R. 122-24-3 distinguishes what is certified from what is merely reported. The document certifies compliance with the provisions of points 1° to 5° of Article R. 172-4 and with the provisions referred to in Article R. 172-5 as specified by order. It also includes the indicators provided for in points 6° and 7° of the same article.

Points 1° to 5° of R. 172-4 correspond to the minimum results to be achieved: the building's energy demand expressed in points, primary energy consumption and non-renewable primary energy consumption in kWh/m²/year, the climate change impact of that consumption in kgCO2eq/m², the climate change impact linked to the building's components assessed over the whole life cycle, and the number of summer discomfort degree-hours expressed in °C.h. Points 6° and 7° are calculated for information: the building's climate change impact over its whole life cycle, and the quantity of carbon taken from the atmosphere and stored in the building in kgC/m².

Decree No. 2026-16 of 15 January 2026, which came into force on 1 May 2026, added a point 8° to Article R. 172-4: the building's renewable primary energy consumption, expressed in kWh/m²/year, also calculated for information. The last sentence of the article now refers to "the provisions of points 1° to 3°, 5°, 6° and 8°", which apply only to the parts of buildings that, in normal use, are heated to a temperature above 12 °C or cooled to a temperature below 30 °C, and to the associated car parks. An investor comparing two assets delivered at different dates must therefore check which version of R. 172-4 applies to the operation: the set of indicators is not the same.

The four certificates not to be confused at completion

Audit files commonly mix several documents of different kinds. The distinction determines the relevance of the document produced.

  • The permit application certificate (R. 122-24-1 CCH), attached to the planning permit application under the conditions provided for in point j of Article R. 431-16 of the French Town Planning Code. It certifies only compliance with points 1° and 5° of R. 172-4 and with the provisions of R. 172-5, and records the client's undertaking to be able, after the declaration of commencement of works, to demonstrate to the persons authorised under Article L. 181-1 compliance with the maximum impact provided for in point 4° of R. 172-4.
  • The RE2020 completion certificate (R. 122-24-3 CCH), with the wider scope described above, attached to the declaration certifying completion and conformity of the works.
  • The thermal regulation certificate (R. 122-24 CCH), which covers the buildings referred to in Article R. 172-10, outside the scope of RE2020, and concerns the requirements of Articles R. 172-11 and R. 172-12. It is drawn up on a form complying with requirements set by order.
  • The acoustic and accessibility certificate (L. 122-10 CCH), which the client sends to the authority that issued the permit on completion of the construction works on new buildings or new parts of existing buildings, and which does not apply to owners building or improving their home for their own use.

To these documents is added, upstream, the certificate under Article L. 122-8 CCH on seismic and cyclone risks, supplied when the planning permit application file is lodged and issued by a technical inspector (contrôleur technique). That last point deserves attention: Article L. 122-8 contained the energy certificate obligation in its version in force from 1 July 2021 to 31 December 2023. Due diligence reports drafted on the basis of old templates still cite that basis. Since 1 January 2024, the seat of the obligation is L. 122-9.

Who may issue the certificate, and on what formal condition

Article R. 122-25 CCH, in the wording resulting from Decree No. 2023-1175, is to be applied strictly:

"The certificate provided for in Articles R. 122-24 and R. 122-24-3 is issued, after a site visit, by one of the following persons: a technical inspector referred to in Article L. 125-1 for any type of building; a person meeting the conditions, referred to in Article L. 271-6, required to carry out the energy performance diagnostic provided for in Article L. 126-26 in the case of a detached or semi-detached house; a body that has certified, within the meaning of Articles L. 433-3 to L. 433-10 of the Consumer Code, the energy performance of the new building or of the new part of the building and that has signed an agreement with the minister responsible for construction, for any type of building; an architect for any type of building; an approved design office, for any type of building."

Two points of control follow. First, the site visit is a condition of validity laid down by the text, and not good practice. A certificate issued on the documents alone, from the calculation files supplied by the project management team (maîtrise d'œuvre), does not satisfy the letter of R. 122-25. In an audit, the question to put to the client is factual: date of the visit, author, visit report.

Second, the approved design office was added to the list by Decree No. 2023-1175, applicable from 1 January 2024. Summary notes that still limit the list to four types of person are out of date.

At legislative level, Article L. 122-12 CCH completes the scheme: the persons or bodies issuing the certificates under Articles L. 122-9, L. 122-10 and L. 122-11 must have taken out professional insurance for this type of mission and, with the exception of the architect, the certifying body under agreement and persons meeting the conditions of Article L. 271-6, must be approved. The signatory's insurance certificate is among the documents to request: it determines whether recourse is worth pursuing if a gap is revealed later.

Transitional measure for earlier operations

Decree No. 2023-1175 provided for a transitional window: the certificates required on completion of the works for buildings for which the planning authorisation application was lodged before 1 January 2024 and for which the declaration certifying completion and conformity of the works is lodged before 1 January 2025 may be made in accordance with the provisions that applied before that decree. On a portfolio delivered between 2023 and 2025, the certificate produced may therefore legitimately follow the old regime. The audit must check the date the permit was lodged and that of the DAACT before concluding that there is non-compliance.

Which buildings are covered: the timetable of R. 172-1 after the decree of 15 January 2026

The scope of RE2020 is defined by the date the planning authorisation was lodged, and not by the delivery date. Article R. 172-1 CCH, in the wording resulting from Decree No. 2026-16 of 15 January 2026, in force since 1 May 2026, layers four strata:

  • residential buildings or parts of buildings for which the planning permit application or prior declaration is lodged from 1 January 2022, excluding cases where the construction gave rise to the signing, before 1 October 2021, of a contract for work within the meaning of Article 1787 of the Civil Code and the application is lodged before 1 September 2022, or of an individual house construction contract governed by Articles L. 231-1 and L. 232-1 CCH;
  • offices and primary or secondary education buildings lodged from 1 July 2022, together with the car parks associated with those buildings;
  • temporary constructions for housing, offices or primary or secondary education referred to in Article R. 421-5 of the Town Planning Code, those erected for a period not exceeding two years, and light leisure dwellings, from 1 July 2023;
  • since 1 May 2026, thirteen new categories for which the application is lodged from that date: media libraries and libraries, atypical teaching buildings, university teaching and research buildings, hotels, early childhood facilities, restaurants, shops, changing rooms on their own, healthcare facilities with accommodation, health establishments, airport terminals, industrial and craft buildings, sports facilities.

Tourist residences with a sleeping area, a kitchen and sanitary facilities are subject to the rules applicable to residential buildings.

Four exclusions appear in paragraph III: buildings that, because of specific constraints linked to their use, must guarantee particular conditions of temperature, humidity or air quality requiring special rules; temporary constructions under Article R. 421-5 of the Town Planning Code or erected for a period not exceeding two years; the construction or extension of buildings with a floor area of less than 50 m²; the extension of buildings with a floor area cumulatively of less than 150 m² and less than 30% of the floor area of the existing premises. Finally, the section does not apply in Guadeloupe, French Guiana, Martinique, La Réunion and Mayotte.

For an investor positioned in hotels, retail or logistics, the extension of 1 May 2026 changes the nature of due diligence: asset classes that were previously outside the scope now generate a completion certificate whose absence will, on resale, be a documentary anomaly.

The certificate in the completion chain: DAACT, post-completion inspection, time bar

The RE2020 certificate is not lodged at the town hall on its own. Article R. 122-24-3 specifies that it is attached to the declaration certifying completion and conformity of the works provided for in Article R. 462-1 of the Town Planning Code. The regime of that declaration, from its author to its effects on resale, is set out in our article on the declaration certifying completion and conformity of the works.

That article, in the wording resulting from Decree No. 2026-674 of 27 July 2026, provides that the declaration "is drawn up by the holder of the planning permit or the development permit or of the decision of non-opposition to the prior declaration, or by the architect or the approved architectural professional, where they directed the works". It is sent by registered post with postal acknowledgement of receipt to the mayor of the municipality or lodged at the town hall against a receipt. The change from "is signed by" to "is drawn up by" deserves to be noted in clients' internal procedures: the way the author of the declaration is formalised has been reworded.

Downstream, Article L. 462-2 of the Town Planning Code provides for the conformity check: the competent authority may, within a period set by decree of the Conseil d'État, carry out or have carried out a post-completion inspection (récolement) of the works and, where they do not conform to the permit issued or to the prior declaration, give the client formal notice to lodge an amending file or to bring the works into conformity. The text adds: "After that period, the competent authority may no longer challenge the conformity of the works."

Where the authority remains silent within the period provided for in Article R. 462-6, Article R. 462-10 of the Town Planning Code, in the wording resulting from Decree No. 2026-117 of 20 February 2026, requires it to issue as of right to the beneficiary of the authorisation or its successors in title, on request, a certificate confirming that the conformity of the works has not been challenged, within fifteen days of the request being submitted. That document is the documentary counterpart of the time bar (forclusion). It should be requested before the asset is put up for sale, not during the exclusivity period.

Acceptance of the works: a contractual requirement before a legal one

None of the texts examined makes acceptance of the works conditional on delivery of the RE2020 certificate. Acceptance remains the act by which the client declares that it accepts the work, with or without reservations, under the Civil Code regime. The certificate arises from a separate administrative obligation, attached to the declaration of completion. On acceptance itself and the transfer of risks that it brings about to the client, see our analysis of acceptance of the works and its effects.

In practice, the link is contractual and it is strong. The special administrative specifications (CCAP) of works contracts commonly make the declaration of acceptance, or the release of the retention (retenue de garantie), conditional on delivery of the as-built file including the regulatory certificates. Property development contracts and acquisitions off plan frequently contain performance undertakings backed by penalties. Asset sale contracts provide for documentary conditions precedent. RE2020 compliance is therefore made contractual where the law does not impose it.

The operational consequence is simple: a client that has not secured, in its works contract, the obligation of the project management team to produce the calculation data and to allow the signatory's site visit finds itself having to have the certificate drawn up after the event, with no contractual leverage over the contractor, and with a risk of a gap between the calculation made for the permit and the work actually carried out. That gap is the real hidden risk of the operation, far more than forgetting the document itself.

Risk exposure after completion: six years of inspection, six years of traceability

Two periods of six years structure the exposure of the holder of the asset, and they do not exactly overlap.

The first is administrative. Article L. 181-1 CCH, in the wording resulting from Ordinance No. 2022-1076 applicable since 1 January 2024, empowers civil servants and public officials authorised or commissioned by the competent State administrative authority or by the competent authority referred to in Articles L. 422-1 to L. 422-3 of the Town Planning Code, or their delegates, and sworn in, to visit buildings subject to the code and to be provided with and take copies of all technical documents relating to the construction. The text specifies that "this right of inspection and of disclosure is exercised during the construction or renovation works on buildings and up to six years after their completion" and that it is exercised between 6 a.m. and 9 p.m., and outside those hours where the premises are open to the public. The old wording naming the prefect and the mayor as holders of the right of inspection no longer matches the wording in force.

The second is documentary. Article R. 172-8 CCH requires that the data used to calculate the values referred to in points 1° to 7° of Article R. 172-4 be "kept by the client, after completion of the works and for at least six years from the lodging of the declaration provided for in Article L. 462-1 of the Town Planning Code". That data is communicated to the first purchaser of the building and, within the limit of the period for which it is kept, on request, to later purchasers, to the persons authorised under Article L. 181-1, to any person responsible for issuing a certificate of taking into account of the construction rules in the section, and to any person responsible for issuing the energy performance diagnostic.

The obligation concerns the calculation data, not the certificate itself. The distinction has a direct practical effect: a second-tier purchaser may demand the calculation files for as long as the retention period runs, which allows it to redo the verification. Once that period has passed, it no longer has them as of right, and the only trace of the initial performance becomes the certificate and, for housing, the information booklet. A well-advised seller keeps the data beyond the statutory minimum: it is a negotiating asset, not an archiving burden.

On the criminal side, caution is called for. Article L. 183-4 CCH, which contained the offence of failing to provide the certificate, was amended by Law No. 2023-175 of 10 March 2023 and no longer shows a version in force that can be consulted. To state an amount of fine without checking the current seat of the offence would be risky. What remains certain is that Article L. 183-1 III CCH provides that, on completion of works on new buildings or new parts of buildings subject to a planning permit, breaches of the provisions of Article L. 171-1 may be recorded by commissioned and sworn officers "on the basis of a certificate issued by a technical inspector referred to in Article L. 125-1, or a person meeting the conditions of Article L. 271-6 or an architect". The certificate is therefore not only a compliance document: it is a basis for recording an offence.

Sale and refinancing: building the evidence file on the asset's operability

For a fund or an investor, the RE2020 certificate of completion reads as one element of the evidence file on the operability of the asset over time. Three areas must be covered.

First area, administrative completeness. The file must bring together the DAACT drawn up and sent in accordance with R. 462-1, the RE2020 certificate attached to it under R. 122-24-3, the acoustic and accessibility certificate under L. 122-10 where it is required, and the certificate of non-challenge of conformity under R. 462-10 or proof that the period under Article L. 462-2 has expired.

Second area, the quality of the signatory. Identity of the signatory against the exhaustive list in R. 122-25, proof of the site visit, approval where required by L. 122-12, and professional insurance certificate for this type of mission. A certificate signed by an unauthorised person is a fragile certificate, and its fragility is revealed at the very moment the purchaser needs it.

Third area, consistency of the indicators. A comparison between the permit certificate under R. 122-24-1, which covers only points 1° and 5° of R. 172-4, and the completion certificate, which covers points 1° to 5° as well as the informative indicators in points 6° and 7°. The indicator in point 4°, relating to the climate change impact linked to the building's components over the whole life cycle, is the one that moves most between design and execution, because it depends on the products and equipment actually installed. That is where substitutions of materials during the works are concentrated, and therefore the gaps.

The special case of housing: information booklet and notarised deed

For residential buildings, the code establishes a direct textual link between the completion certificate and transfer of ownership. Article R. 126-34 CCH lists among the documents that certify the energy performance of the dwelling, and that must appear in the housing information booklet, "the document drawn up by the client certifying that the energy and environmental performance requirements have been taken into account, where required under Article R. 122-24-3", alongside the energy performance diagnostic (DPE), the thermal regulation certificate under R. 122-24, label or certification certificates and any energy audit meeting the conditions of Article L. 126-28-1.

Article L. 126-35-10 CCH closes the loop: the information booklet is passed to the purchaser on any transfer of the dwelling, as it stands at the time of the transfer, no later than the date the notarised deed (acte authentique) is signed, and the purchaser acknowledges this in the notarised deed. In the sale of residential units, the absence of the RE2020 certificate from the booklet therefore shows up in the deed itself, under the notary's eye. It is the most predictable point of friction in a bulk sale of new homes. The content of this booklet and the conditions for passing it on are dealt with separately in our article on the housing information booklet.

Conclusion

The RE2020 completion certificate is not an end-of-works formality. Since 1 January 2024, it certifies compliance with the performance requirements, it commits its authorised signatory after a site visit, it forms part of the DAACT, it can serve as a basis for recording an offence, and it feeds the housing information booklet handed to each purchaser. It records in writing the performance of the asset at a fixed date, and that is precisely why it has become a price factor.

The position taken is this: the certificate should be treated as a contractual deliverable of the works contract, not as an administrative step after completion. The cost of belated regularisation is low; the cost of a gap revealed in due diligence is negotiated in basis points on the price or in a retention held in escrow.

Before any sale or refinancing of an asset delivered less than six years ago, have three points checked by an adviser independent of the project management team: the signatory's authorisation against the exhaustive list in R. 122-25 and their professional insurance, the consistency between the permit indicators and those at completion, and the actual availability of the calculation data kept under R. 172-8. At the same time, request the certificate of non-challenge of conformity under R. 462-10: it is issued as of right within fifteen days of the request, and its absence from the file is the first question the purchaser will ask.

Frequently asked questions

Is the RE2020 completion certificate mandatory for all new buildings?

No. The obligation in Article L. 122-9 CCH concerns construction works on buildings subject to a planning permit and renovation works on existing buildings subject to a planning permit, and the certificate under R. 122-24-3 concerns the buildings referred to in Articles R. 172-1 and R. 172-3. The scope depends on the date the authorisation was lodged: housing from 1 January 2022, offices and primary or secondary education from 1 July 2022, temporary constructions from 1 July 2023, and thirteen new categories from 1 May 2026 under Decree No. 2026-16. Constructions or extensions with a floor area of less than 50 m² are among those excluded, and the section does not apply in Guadeloupe, French Guiana, Martinique, La Réunion and Mayotte.

Who can sign the RE2020 completion certificate?

Article R. 122-25 CCH sets an exhaustive list: a technical inspector referred to in Article L. 125-1 for any type of building, a person meeting the conditions of Article L. 271-6 required to carry out the DPE in the case of a detached or semi-detached house, a body that has certified the energy performance of the new building and has signed an agreement with the minister responsible for construction, an architect for any type of building, and an approved design office for any type of building. The certificate must be issued after a site visit. Article L. 122-12 adds a requirement of professional insurance for this type of mission and, except for the architect, the certifying body and the persons under Article L. 271-6, an approval.

Does the absence of the certificate prevent acceptance of the works?

No text legally makes acceptance conditional on delivery of the RE2020 certificate: they are two acts of different kinds, one contractual, the other administrative and attached to the declaration certifying completion and conformity of the works. In practice, works contracts and development contracts frequently make the declaration of acceptance of the works, the release of the retention or the final payment under the contract conditional on delivery of the as-built file including the regulatory certificates. The requirement therefore exists, but it is contractual. It must be expressly stipulated, failing which the client loses its leverage over the project management team.

Can a purchaser demand the RE2020 calculation data for the asset it is buying?

Yes, within the limits set by Article R. 172-8 CCH. The data used to calculate the values referred to in points 1° to 7° of Article R. 172-4 is kept by the client after completion of the works and for at least six years from the lodging of the declaration provided for in Article L. 462-1 of the Town Planning Code. It is communicated to the first purchaser of the building and, within the limit of the period for which it is kept, on request, to later purchasers. The obligation concerns the calculation data, and not the certificate itself, which for housing falls within the information booklet.

For how long can the authorities check RE2020 compliance after delivery?

Article L. 181-1 CCH provides that the right of inspection and of disclosure of all technical documents held by authorised or commissioned and sworn officers is exercised during the construction or renovation works and up to six years after their completion, between 6 a.m. and 9 p.m., and outside those hours where the premises are open to the public. At the same time, Article L. 462-2 of the Town Planning Code provides that after the post-completion inspection period set by decree of the Conseil d'État has expired, the competent authority may no longer challenge the conformity of the works. Those two periods are independent: the time bar in town planning matters does not neutralise the right of inspection under the CCH.

What is the difference between the certificate attached to the planning permit and the one attached to the completion declaration?

The certificate under Article R. 122-24-1 is attached to the planning permit application under the conditions of point j of Article R. 431-16 of the Town Planning Code. It certifies only compliance with points 1° and 5° of Article R. 172-4 and with the provisions of R. 172-5, and contains the client's undertaking to be able to demonstrate, after the declaration of commencement of works, compliance with the maximum impact in point 4° of R. 172-4. The certificate under Article R. 122-24-3, attached to the DAACT, covers points 1° to 5° of R. 172-4 as well as the provisions of R. 172-5, and includes the indicators in points 6° and 7°. It is the comparison of the two documents that reveals the gaps between design and execution.

Are certificates issued for operations before 2024 still valid?

Decree No. 2023-1175 of 12 December 2023 provided for an express transitional measure: the certificates required on completion of the works for buildings for which the planning authorisation application was lodged before 1 January 2024 and for which the declaration certifying completion and conformity of the works is lodged before 1 January 2025 may be made in accordance with the provisions that applied before that decree. For those operations, a certificate issued under the old regime is not irregular. The audit must therefore systematically note the date the permit was lodged and that of the DAACT before concluding that there is a failure of RE2020 compliance.

Votre situation ressemble-t-elle à celle-ci ?

Quatre questions suffisent à situer votre position, le délai qui vous reste et ce qu'il faut vérifier en priorité. Vous décidez ensuite si vous en parlez au cabinet.

Décrire ma situation
Sans engagement – réponse du cabinet sous quarante-huit heures ouvrées.
• Vous êtes concerné ?

Defects that appeared after handover?

One-year completion warranty, two-year warranty, ten-year liability: which one protects you depends on the nature of the defect and the date of handover.

construction
re2020-completion-certificate-the-document-for-acceptance-and-resale
Questionnaire
×
Merci, votre demande est bien parvenue au cabinet. Une réponse vous sera adressée sous quarante-huit heures ouvrées.
L’envoi n’a pas abouti. Vous pouvez écrire directement à contact@avocats-gloria.com.

Vos réponses aux questions précédentes sont jointes à votre message. Réponse sous quarante-huit heures ouvrées.

Ces questions ne constituent pas une consultation juridique et ne remplacent pas l’examen de vos pièces. Les informations transmises servent uniquement à répondre à votre demande et ne sont pas cédées à des tiers.