Articles

Real environmental obligation: the burden that follows the asset for 99 years

A buyer signing a preliminary agreement on a peri-urban land portfolio, an investor taking over an industrial asset with a land reserve, a fund positioning itself on a discounted plot: all of them reason in terms of buildability, rights of way, soil condition and potential liabilities. Few of them ask whether a real environmental obligation contract (obligation réelle environnementale, ORE) exists, even though this undertaking passes automatically to successive owners and can run for up to ninety-nine years. The burden is contractual in origin and real in its effects: it encumbers the asset, not only the signatory. This article looks at the ORE from the standpoint of the buyer and the lender: how to detect it in due diligence, how to measure its impact on the usability and valuation of the asset, and what room for renegotiation or exit remains once the deed has been registered.

What the real environmental obligation contract creates, and who bears it

Article L. 132-3 of the French Environmental Code, introduced by Law No. 2016-1087 of 8 August 2016 on the recovery of biodiversity, allows owners of real property to enter into a contract with a public authority, a public body or a private legal entity acting for the protection of the environment, in order to create real obligations.

Three elements structure the mechanism and must be read literally.

First, the counterparty. The text closes the list: a private legal entity may be a party only if it acts for the protection of the environment. A neighbour, a developer or an operating company therefore cannot, on its own, be the beneficiary of an ORE. In due diligence, the status of the counterparty is a first point of control: it determines the validity of the real environmental obligation contract. The general method for the audit that precedes an acquisition is set out in our article on property due diligence and how it proceeds.

Second, the purpose. The obligations must aim at the maintenance, conservation, management or restoration of elements of biodiversity or ecological functions. The scope is wide but bounded: an obligation that is purely landscape-related, agronomic or architectural, with no link to biodiversity or ecological functions, falls outside the statutory framework. A hybrid clause, combining an ecological undertaking with operating constraints, deserves to be examined item by item.

Third, the subjective scope, which is the core of the risk for the investor. The owner creates the obligations at their own expense and at the expense of subsequent owners of the property. This is automatic transmissibility: the buyer does not adhere, it bears. The text requires no specific consent on its part for the burden to be enforceable against it. Practitioners often speak of an environmental easement; the expression is convenient, but no text that we have read settles the exact characterisation (a right in rem sui generis, a real charge, a personal easement). This uncertainty over characterisation is not theoretical: it governs the conditions for extinction, clearing and division of the burden, questions on which legal commentators remain divided.

Authentic form and tax neutrality of the deed

The contract is drawn up in authentic form. This requirement fits with Article 710-1 of the French Civil Code, under which any deed or right, in order to give rise to land registration formalities, must result from a deed received in authentic form by a notary practising in France, from a court decision or from an authentic deed issued by an administrative authority. An ecological undertaking granted by a private instrument, even if deposited among a notary's records, cannot be given that characterisation.

For tax purposes, the legislature has neutralised the cost of the deed: the contract is not subject to registration duties, does not give rise to the land registration tax provided for in Articles 662 and 663 of the French General Tax Code, nor to payment of the property security contribution provided for in Article 879 of the same Code. This relative absence of cost explains the quiet spread of the mechanism: it costs little to put in place, and nothing obliges the signatory owner to assess its effects on resale value.

Duration: ninety-nine years, and only since 2022

The point deserves particular attention because it is frequently misdated in commentary.

The duration of the obligations, the reciprocal undertakings and the possibilities of revision and termination must appear in the contract. The duration provided for in the contract may not exceed ninety-nine years.

The second sentence results from Article 191 of Law No. 2022-217 of 21 February 2022. In its earlier wording, applicable until 22 February 2022, Article L. 132-3 contained no limit on duration. The direct operational consequence is that, for a contract signed between 2016 and February 2022, the stipulated duration may exceed ninety-nine years, or even be perpetual or indefinite depending on the drafting adopted. The auditor therefore cannot presume a ceiling; the duration clause must be read in the deed itself and the date of signature checked.

The text also requires the contract to state the duration, the reciprocal undertakings and the possibilities of revision and termination. This last requirement is the buyer's main lever. A real environmental obligation contract that is silent on revision and termination does not comply with the letter of Article L. 132-3; the text does not specify the sanction for this failing, but the argument is a serious one in a negotiation as in litigation. Conversely, a contract that provides for periodic revision, a right of termination at a fixed date or a mechanism for substituting parcels offers an identifiable way out, which must be costed before signing.

Detecting the ORE: mapping the due diligence checkpoints

The ORE does not reveal itself in a standard acquisition file. It has to be looked for.

  • The mortgage status certificate and the thirty-year chain of title, to be re-read with an explicit instruction to look for environmental burdens and not only security interests.
  • The authentic deed itself, to be requested in full: the duration clause, the reciprocal undertakings, the provisions on revision and termination, and the identity of the beneficiary cannot be reduced to a mention in the title.
  • The national geographic information system provided for in Article L. 163-5 of the French Environmental Code, which geolocates and describes measures compensating for harm to biodiversity, is publicly accessible on the internet and is fed by project owners. Where the ORE serves as the vehicle for compensation, the land is meant to appear in it.
  • The leases and occupation agreements in force, which condition the very lawfulness of implementing the ORE where a rural lease exists (see below).
  • The resolutions of the municipality or of the EPCI with its own tax powers (a group of municipalities) on exemption from property tax on undeveloped land, which are a tax indicator that a contract exists.

The precise rules on land registration of the ORE, and therefore the exact conditions of its enforceability against a buyer who was not informed of it, are not settled by Article L. 132-3 itself. The requirement of authentic form laid down by the text and the mechanism of Article 710-1 of the French Civil Code point towards registration, but prudence dictates not basing an acquisition strategy on the idea that an unregistered ORE would be unenforceable. The opposite reflex is safer: audit, then contract for a specific warranty.

ORE and ecological compensation: two distinct regimes, often superimposed

Article L. 132-3 merely states that these obligations may be used for compensation purposes. The ORE is therefore not, by nature, a compensatory measure: it is a land-based vehicle that may carry one. Confusion between the two regimes is the costliest source of error in an audit, because the obligations and the sanctions do not fall on the same persons.

Compensation is the responsibility of the project owner, not of the landowner

Article L. 163-1, most recently rewritten by Article 33 of Law No. 2026-796 of 18 August 2026, in force since 20 August 2026, provides that compensation measures aim to avoid net losses of biodiversity, cannot replace avoidance and reduction measures, and that if the harm can be neither avoided, nor reduced, nor satisfactorily compensated, the project is not authorised as it stands. Paragraph II provides for three ways of satisfying the obligation: direct implementation, contractual recourse to a compensation operator, or acquisition of compensation, restoration or renaturation units within a natural site for compensation, restoration and renaturation. And it sets out a rule that the buyer must keep in mind:

In all cases, the project owner remains solely responsible towards the administrative authority that prescribed these compensation measures.

The same 2026 rewriting adds location rules that directly concern landholders: implementation as a priority within the preferential renaturation zones identified by the territorial coherence schemes (schémas de cohérence territoriale) and by the planning and programming guidelines covering areas to be renatured, and, where the measures concern agricultural land, implementation as a priority on uncultivated land or land with low agronomic potential, with contracting preferably with farmers or implementation in association with them. For an investor holding low-yield agricultural land in a high-pressure area, these paragraphs create both pressure and an opportunity for monetisation.

The contract with the third-party owner

Where compensation measures are implemented on land belonging neither to the person subject to the obligation nor to the compensation operator that person has appointed, Article L. 163-2 requires a contract with the owner and, where applicable, the tenant or farmer, defining the nature of the measures, how they are to be implemented and their duration. This contract may take the form of an ORE, but may also use other vehicles. The audit must therefore distinguish what falls under Article L. 132-3 from what falls under Article L. 163-2: durations, termination rights and financial consideration do not follow the same logic.

The risk of sanction: whom does it really concern

Article L. 163-4 governs the consequences of non-performance: formal notice by the administrative authority under the conditions laid down in Article L. 171-8, then, on expiry of the time limit given, performance by the authority in place of that person and at that person's expense, by entrusting the work to a compensation operator or by acquiring compensation, restoration or renaturation units. To this are added further requirements where the measures are ineffective in achieving ecological equivalence, the possibility of requiring financial guarantees to be put in place, and an interplay with the administrative fine and the deposit provided for in paragraph II of Article L. 171-8.

These sanctions are aimed at the person subject to the compensation obligation. They do not, in themselves, strike the landowner who signed an ORE. However, the owner's exposure arises in contract: if the project owner is subject to performance by the authority at its own cost, it will turn against the holder of the land on the basis of the contract concluded with that holder. The audit must therefore identify re-invoicing clauses, undertakings as to ecological results and any penalty clauses, points on which Article L. 132-3 is silent and which depend entirely on the drafting of the deed.

Where the asset is the land underlying an approved site

The most restrictive scenario is that of an asset serving as the land underlying a natural site for compensation, restoration and renaturation (SNCRR). Since Article 15 of Law No. 2023-973 of 23 October 2023, this is the terminology to use: the former expressions "natural compensation sites" and "compensation units" belong to the earlier wording.

Article L. 163-1 A makes these sites subject to prior approval by the administrative authority, granted having regard in particular to the expected ecological gain, the integration of the site into ecological continuities, its surface area and the human pressures bearing on it. The ecological gain is identified by compensation, restoration or renaturation units, which may be sold to any other public or private person. The text also opens the possibility of allocating carbon credits under the low-carbon label, subject to the principles set out in Article L. 229-55 and to the method approved by the minister responsible for the environment. For an investor, the encumbered land then ceases to be a pure liability: it becomes an income-generating asset, whose valuation depends on the depth of the market for units.

The counterpart is a lasting management burden. Article D. 163-6 requires approved sites to guarantee the creation of the ecological gains for which approval was sought and then their maintenance until the end of the approval period, to be monitored and evaluated, to send the competent authority each year the information needed to update the national geographic information system, and to provide an annual report including in particular the monitoring of units sold in the form of a sales register. This register is a first-rate audit document: it reveals the volume of units already sold, and therefore the extent of the commitments made to third-party buyers.

Transfer of the approval on a sale

Article D. 163-10 governs the exit. The holder of an approval may transfer it, but the new holder must, at least three months before the effective date of the transfer, declare it to the competent authority, and show that it has the necessary technical and financial capacities as well as the rights allowing the obligations provided for by the approval to be implemented on the underlying land. The authority has two months from receipt of the complete file to issue an acknowledgement or to refuse the transfer by reasoned letter; if there is no reply within that period, the transfer is authorised. Buyers of units are informed of the transfer as soon as the new holder has been authorised.

This timetable governs the sequence of the transaction. A closing fixed without allowing for the three-month declaration period exposes the buyer to holding an asset whose approval it cannot use. The completion clause must therefore be tied to this sequence, with a milestone for filing the declaration before signature of the authentic deed. Conditions precedent and the other provisions of a preliminary agreement are dealt with separately in our article on the essential clauses of a promise to sell.

Usability of the asset: the interferences to measure before the decision

Rural lease: absolute nullity at stake

Article L. 132-3 lays down a rule whose sanction is exceptionally severe: an owner who has granted a rural lease over the land may not, on pain of absolute nullity, implement a real environmental obligation except with the prior agreement of the tenant and subject to the rights of third parties. Failure to reply to a request for agreement within two months amounts to acceptance, and any refusal must be reasoned.

In due diligence on a let rural or peri-urban asset, the check is binary: does the file contain proof of the tenant's agreement, or of expiry of the two-month period following a proper request? Failing that, the absolute nullity of the ORE contract is a major renegotiation lever and, depending on the circumstances, a way out. This inquiry goes hand in hand with an examination of the environmental clauses of the lease itself: Article L. 411-27 of the French Rural and Maritime Fishing Code strictly limits the cases in which clauses requiring practices that preserve water resources, biodiversity, landscapes, product quality, soils and air may be included in leases, and it prohibits relying on the tenant's environmental practices in support of a claim for termination.

The text also expressly reserves hunting: implementation of an ORE may in no way call into question either the rights linked to the exercise of hunting or those relating to game reserves. For an asset whose value includes a let hunting right, the reservation should be noted in the audit report.

As regards other tenants, whether under a commercial lease, a building lease or a precarious occupation agreement, Article L. 132-3 does not provide an equivalent requirement of agreement. The silence of the text does not allow one to conclude that there is no constraint at all: the interplay between an ORE and the rights of the tenant in place is then settled under the general law of leases and the contractual liability of the landlord, who owes delivery and peaceful enjoyment.

The tax lever, and its filing condition

Article 1394 D of the French General Tax Code, in the wording resulting from Article 130 of Law No. 2020-1721 of 29 December 2020, allows municipal councils and the deliberative bodies of EPCI with their own tax powers to exempt from property tax on undeveloped land, for their share and for the whole duration of the contract, undeveloped properties whose owner has entered into an ORE. Two points should be noted.

The exemption is optional and requires a resolution adopted under the conditions provided for in paragraph I of Article 1639 A bis. It is therefore never acquired by the contract alone. And above all, it depends on a step taken by the owner: the owner sends to the tax office of the place where the properties are located, before 1 January of the year following that in which the contract was signed, a declaration containing all the information needed to identify the parcels concerned, together with a copy of the contract. Where the declaration is filed late, the exemption applies for the period remaining after 31 December of the year in which it is filed.

This exemption must not be confused with the neutrality of the deed as regards registration duties, land registration tax and the property security contribution, which applies as of right. In a valuation model, the saving on TFPNB (property tax on undeveloped land) should be taken into account only after checking the applicable resolution and that the seller has actually completed the filing formality.

Room for renegotiation and exit

Three levers, ranked by strength.

The first is textual: Article L. 132-3 requires that the possibilities of revision and termination appear in the contract. The buyer must therefore identify the revision scenarios stipulated, their frequency, the authority empowered to trigger them, and the financial consequences. A contract providing for revision at regular intervals, or termination if the ecological object disappears, changes the economic horizon of the asset.

The second is the regularity of the deed: status of the counterparty against the closed list in the text, a purpose genuinely linked to biodiversity or ecological functions, authentic form, and, where there is a rural lease, the tenant's prior agreement on pain of absolute nullity. Each of these points is an angle of attack or, at the very least, an argument for a price reduction.

The third is purely contractual and plays out between seller and buyer. In the absence of any text governing the price reduction or compensation of the encumbered owner, protection comes through drafting: an express statement by the seller on the existence and content of any ORE, a specific environmental liability warranty not capped by the general warranty, a condition precedent of obtaining the beneficiary's agreement to an amendment, an escrow indexed to the annual management cost, and a price adjustment if the register of unit sales reveals commitments greater than those disclosed. On the contractual allocation of remediation costs between seller and buyer, see our analysis of the environmental liability warranty in the acquisition of a property asset.

On the seller's side, the exposure is symmetrical. Article 1112-1 of the French Civil Code requires the party who knows information of decisive importance for the other party's consent to inform that party of it, where the latter legitimately does not know the information or relies on its counterparty. This duty does not extend to an estimate of the value of the performance, but it readily covers the existence of a real burden encumbering the property for several decades. The parties may neither limit nor exclude this duty. Its breach engages the liability of the person bound by it and may lead to annulment of the contract under the conditions provided for in Articles 1130 et seq. Concealing an ORE to protect a price is therefore a losing trade-off.

Our recommendations

The real environmental obligation is not a marginal mechanism confined to natural land. It has become an instrument for securing land for compensation operators, local authorities and SNCRR sponsors, and it is becoming a lasting feature of chains of title. Our reading is clear: treating the ORE as a mere ancillary environmental easement is an error of analysis. Its horizon, up to ninety-nine years for contracts after 22 February 2022 and with no statutory ceiling for earlier contracts, exceeds the holding period of any investor. The burden outlasts the investment decision.

Before signing any promise on undeveloped land, or built land with a land reserve, require the authentic ORE deed in its entirety, not a mention in the title; check the date of signature before reasoning on a ceiling for the duration; where there is a rural lease, request proof of the tenant's prior agreement or of expiry of the two-month period; and if the asset carries an approved SNCRR, align your closing timetable with the three-month declaration period provided for in Article D. 163-10. An audit carried out after the deed offers no more than a dispute; carried out before, it offers a price reduction or a withdrawal.

Frequently asked questions

Is a real environmental obligation enforceable against a buyer who did not sign it? Yes, that is the very purpose of the mechanism. Article L. 132-3 of the French Environmental Code allows the owner to create the obligations at the owner's expense and at the expense of subsequent owners of the property. The text requires no specific consent from the buyer. The question of the exact rules on land registration and of enforceability against an uninformed buyer is not settled by that article: it calls for an examination of the deed and of the mortgage status certificate case by case.

What is the maximum duration of a real environmental obligation contract? Since Article 191 of Law No. 2022-217 of 21 February 2022, Article L. 132-3 states that the duration provided for in the contract may not exceed ninety-nine years. This ceiling did not exist before: the wording in force until 22 February 2022 contained no limit on duration. For a contract signed between 2016 and February 2022, the stipulated duration must therefore be read in the deed without presuming a statutory maximum.

Can an ORE be terminated? The text does not provide for a statutory right of unilateral termination. It does, however, require that the duration of the obligations, the reciprocal undertakings and the possibilities of revision and termination appear in the contract. The exit is therefore first of all contractual: it depends on the clauses negotiated at signing. In the absence of any provision on these points, the irregularity of the deed under Article L. 132-3 is a serious negotiating argument.

Can an ORE be entered into over land let under a rural lease? Yes, but on strict conditions. An owner who has granted a rural lease may not, on pain of absolute nullity, implement an ORE except with the prior agreement of the tenant and subject to the rights of third parties. Failure to reply to a request for agreement within two months amounts to acceptance, and any refusal must be reasoned. The absence of proof of that agreement in the acquisition file is a priority audit point.

Does the ORE give entitlement to a property tax exemption? Not automatically. Article 1394 D of the French General Tax Code allows municipal councils and the deliberative bodies of EPCI with their own tax powers to exempt from TFPNB, for their share and for the whole duration of the contract, undeveloped properties encumbered by an ORE. The exemption requires a resolution and a declaration by the owner to the tax office before 1 January of the year following that in which the contract was signed, together with a copy of the contract. Late declaration: the exemption applies only for the period remaining after 31 December of the year in which the declaration is filed.

How can one check whether a plot carries ecological compensation measures? Article L. 163-5 of the French Environmental Code provides that measures compensating for harm to biodiversity are geolocated and described in a national geographic information system that is publicly accessible on the internet and fed by project owners. This search supplements, without replacing, the analysis of the mortgage status certificate and the chain of title. For an approved site, the annual report provided for in Article D. 163-6, including the register of unit sales, gives a view of the commitments made to third parties.

If compensation measures are not performed, who is sanctioned? Article L. 163-4 targets the person subject to the obligation to implement the compensation measures. The administrative authority serves formal notice on that person under the conditions of Article L. 171-8, and may then have the measures performed by the authority in place of that person and at that person's expense, order further requirements if the measures are ineffective as regards ecological equivalence, and require financial guarantees. Article L. 163-1 adds that the project owner remains solely responsible towards the administrative authority. The exposure of the landowner, for its part, arises in contract.

The simulator below calculates the end of your cooling-off period and tells you whether you can withdraw from the purchase without losing the sums paid.

Votre situation ressemble-t-elle à celle-ci ?

Quatre questions suffisent à situer votre position, le délai qui vous reste et ce qu'il faut vérifier en priorité. Vous décidez ensuite si vous en parlez au cabinet.

Décrire ma situation
Sans engagement – réponse du cabinet sous quarante-huit heures ouvrées.
• Vous êtes concerné ?

A defect discovered after the sale?

The time limit for taking action runs not from the sale but from the discovery of the defect, and it is shorter than people think.

vices
real-environmental-obligation-burden-that-follows-the-asset-99-years
Questionnaire
×
Merci, votre demande est bien parvenue au cabinet. Une réponse vous sera adressée sous quarante-huit heures ouvrées.
L’envoi n’a pas abouti. Vous pouvez écrire directement à contact@avocats-gloria.com.

Vos réponses aux questions précédentes sont jointes à votre message. Réponse sous quarante-huit heures ouvrées.

Ces questions ne constituent pas une consultation juridique et ne remplacent pas l’examen de vos pièces. Les informations transmises servent uniquement à répondre à votre demande et ne sont pas cédées à des tiers.

← Question précédente

Gloria Avocats, your trusted legal partner

By email or by telephone, the firm will answer all your questions.

• Contact us