The situation recurs in renovation projects for commercial assets just as in heavy restructurings of residential units: the works come to an end, the project owner (maître d'ouvrage) takes back the keys, pays the final instalment, brings the asset into use, and nobody signs a report of acceptance (procès-verbal). Eighteen months later, water infiltration appears at the foot of a façade, or a technical floor starts to warp. The first question put to the French lawyer is never one of liability: it is one of dates. Without a date of acceptance (réception), there is no completion warranty, no performance warranty for equipment, no ten-year liability, and the structural damage insurer (assureur dommages-ouvrage) will immediately point to the absence of a starting point. This guide sets out how tacit acceptance of works is established, which acts characterise it, which date to adopt, and which documents to secure before applying for an investigative measure under Article 145 of the French Code of Civil Procedure.
Acceptance is the sole triggering event of the statutory warranties
Article 1792-6 of the French Civil Code lays down a brief but structuring definition:
Acceptance is the act by which the project owner declares that it accepts the work, with or without reservations. It takes place at the request of the more diligent party, either by agreement or, failing that, by the court. It is, in any event, pronounced on an adversarial basis.
Three lessons for the investor. First, the text recognises only two routes, by agreement and by the court. It nowhere mentions tacit acceptance: that is a case-law construction, forged by the 3rd Civil Chamber of the Cour de cassation, which infers from the project owner's conduct an unequivocal intention to accept the work. No article of the Civil Code defines it, which explains why its date is always disputed and why it ultimately falls to the sovereign assessment of the trial court on the evidence produced.
Second, acceptance conditions the whole architecture of the warranties. Article 1792-4-1 discharges the builder from the liability provided for in Articles 1792 to 1792-2 after ten years from acceptance of the works. Article 1792-6 sets the completion warranty (garantie de parfait achèvement) for a period of one year from acceptance. Article 1792-3 imposes a performance warranty on items of equipment for a minimum period of two years from its acceptance. Article 1792-4-3 confines other actions against builders and their subcontractors to a period of ten years from acceptance. The ten-year warranty starting point is therefore neither the physical completion of the works, nor the handover of the keys as such, nor the issue of the final invoice: it is acceptance, and acceptance alone.
Finally, Article 1792-6 provides an often overlooked way out: acceptance by the court. Where the contractor refuses to sign the report or has disappeared, the project owner may apply to the court for acceptance to be pronounced, if necessary with retroactive effect to a given date. This route is frequently sought in the alternative, in the same proceedings, where tacit acceptance is disputed.
Acceptance, completion, delivery: three notions not to be confused
Completion is a physical state of the work. Delivery is the physical handover of the property. Acceptance is a legal act of approval. A work may be completed without being accepted, and accepted while finishing work remains to be carried out. For the investor, the stakes are concrete: the declaration certifying completion and compliance of the works filed at the town hall, the project manager's certificate of completion or the certificate of conformity do not amount to acceptance. At best they are indications among others in reconstructing a date.
Taking possession and paying the balance: the two decisive indications
The case law of the 3rd Civil Chamber traditionally holds that tacit acceptance requires an unequivocal intention on the part of the project owner to accept the work. Two forms of conduct are, in practice, systematically examined: actual taking of possession and full payment of the price.
Actual taking of possession of the work
Taking of possession is shown by dated facts: handover of the keys, installation of furniture, connection of energy supply contracts in the project owner's name, signature of a lease and entry of the tenant into the premises, resumption of trading in a commercial unit, taking out a multi-risk building insurance policy on the completed work. For an investor, the effective date of the lease or the tenant's entry inventory (état des lieux d'entrée) is often the most probative document, because it is adversarial and time-stamped.
Taking of possession alone is rarely held to be sufficient. It is all the more effective where it is peaceful, prolonged and unaccompanied by any contemporaneous protest about the quality of the work. Conversely, occupation forced by urgency, concurrent with formal notices to complete or to remedy defective workmanship, weakens the argument.
Payment of the balance and the retention trap
Full payment of the price is the mirror-image indication. Paying the last works instalment without any written reservation amounts, in practice, to showing satisfaction. This is where a paradox arises that many finance departments do not anticipate.
Law No. 71-584 of 16 July 1971 authorises, on private works contracts, a retention (retenue de garantie) of no more than 5 per cent of the instalments paid, contractually securing performance of the works in order to satisfy, where applicable, the reservations made at acceptance. The project owner must deposit the corresponding sum with a depositary accepted by both parties or, failing that, appointed by the president of the tribunal judiciaire or of the commercial court, unless the contractor provides a personal and joint guarantee from a financial institution appearing on a list fixed by decree.
Applying the retention does not suspend acceptance and does not prevent tacit acceptance from being found. But paying the whole of the balance without keeping either a retention or a guarantee, and without formalising any reservation, deprives the project owner of its main argument for disputing acceptance. Many disputes turn on a balance payment made by the finance department without consulting the asset manager, who had in fact noted defects. The role of the retention in clearing reservations, and what remains of it if the contractor fails, are examined in our article on the retention.
What can overturn the indication
Tacit acceptance is open to dispute. A site abandoned during execution, a contractor placed in judicial liquidation before the premises were taken back, written reservations contemporaneous with the taking of possession, a refusal to pay the balance expressly reasoned by non-completion, are all factors that the courts weigh in order to rule out an unequivocal intention to accept. These solutions are matters of case law and of assessment of the factual circumstances: no text codifies them, and it would be imprudent to build a strategy on a general rule in this area.
The date adopted: a choice to be investigated as a question of evidence
Where taking of possession and payment of the balance are separated in time, sometimes by several months, which date should be adopted? No written rule settles the matter. The date is the one the judge will infer from the evidence produced, which leads to two strategic consequences.
First consequence: the parties do not have the same interest. The builder and its insurer will argue for the earliest date, so that the ten years of Article 1792-4-1 and the two years of Article 1792-3 begin to run sooner. The project owner will argue for the latest date, or for the absence of acceptance, depending on whether the defects fall under ten-year liability or under ordinary contractual liability. The choice is made case by case, according to the nature of the defects and the age of the facts.
Second consequence: the question of acceptance without reservations. Where acceptance is tacit, there is by definition no report and therefore no reservation recorded. Builders draw from this the argument that acceptance took place without reservations and that defects that were apparent on the day possession was taken are covered. Article 1792-6 mentions only two channels for reporting them, either by means of reservations recorded in the report of acceptance, or by written notification for those revealed after acceptance. In the absence of a report, the second channel becomes the project owner's only tool, and it must be used immediately and in writing.
The documents that reconstruct a date
Reconstructing a date of tacit acceptance is a matter of assembling the file. The most useful documents, in a dispute over the renovation of an asset, are the following:
- the report of handover of the keys or the signed delivery note, even if summary
- the tenant's entry inventory and the effective date of the lease
- the energy, water and telecommunications supply contracts in the project owner's name, with their connection date
- the last works instalment, the final invoice, the transfer order and the corresponding bank statement
- the project manager's site meeting minutes and any clearing of pre-acceptance reservations
- contemporaneous written exchanges, including emails, on the condition of the work
- a report by a commissaire de justice (bailiff), where one was drawn up when possession was taken
- the ten-year insurance certificates of the contractors involved, which Article L. 243-2 of the French Insurance Code requires to be attached to the quotes and invoices of insured professionals
The chronology of the warranties once the date is fixed
Year 1: the completion warranty
The contractor is bound by the completion warranty for a period of one year from acceptance. It covers all defects notified by the project owner, regardless of seriousness, but it does not extend to work necessary to remedy the effects of normal wear and tear or of use.
The mechanism is contractual and operational. Repair periods are fixed by mutual agreement; failing agreement or in the event of non-performance within the period fixed, the work may, after a formal notice that has remained unsuccessful, be carried out at the expense and risk of the defaulting contractor. Performance is then recorded by mutual agreement or, failing that, by the court.
For a project owner in a situation of tacit acceptance, the sequence to follow is therefore: detailed written notification of the defects, proposal of a period for performance, formal notice by registered letter in the event of inaction, then performance at the contractor's expense and risk after quotes from third-party contractors. Each step must be dated and kept, because it conditions the later invoicing of the additional cost. The formal notice and the performance at the builder's expense and risk are discussed in our article on the completion warranty.
Year 2: the performance warranty
Items of equipment are covered by a performance warranty (garantie de bon fonctionnement) of a minimum period of two years from acceptance, under Article 1792-3. For a commercial asset, Article 1792-7 calls for particular vigilance: items whose exclusive function is to allow a professional activity to be carried on within the work are not regarded as items of equipment of the work. The characterisation is made item by item and governs the very admissibility of the claim.
Ten years: ten-year liability and residual actions
Article 1792 establishes strict liability of the builder towards the owner or the purchaser of the work for damage that compromises the structural soundness of the work or that, affecting it in one of its constituent elements or one of its items of equipment, renders it unfit for its purpose, unless an external cause is proved. Article 1792-4-1 discharges the builder after ten years from acceptance.
Outside those regimes, Article 1792-4-3 provides that liability actions against the builders designated in Articles 1792 and 1792-1 and their subcontractors are time-barred after ten years from acceptance of the works. Actions against the subcontractor are governed by Article 1792-4-2: ten years for damage falling under Articles 1792 and 1792-2, two years for damage affecting the items of equipment referred to in Article 1792-3, in both cases from acceptance.
Insurance: how it fits with the date of acceptance
The structural damage insurance of Article L. 242-1 of the French Insurance Code takes effect after the expiry of the completion warranty period referred to in Article 1792-6 of the Civil Code. Two statutory exceptions allow it to be called on earlier: before acceptance, after an unsuccessful formal notice, where the contract for the hire of work is terminated because of the contractor's failure to perform its obligations; after acceptance, after an unsuccessful formal notice, where the contractor has not performed its obligations. The formal notice is therefore not a formality: it is the condition for the cover to be triggered during the first year.
An investor that is a legal entity must check whether it was itself subject to the requirement. The obligation to take out structural damage insurance does not apply to public-law legal entities, nor to legal entities carrying on an activity whose scale exceeds the thresholds referred to in the last paragraph of Article L. 111-6, where those entities have construction work carried out on their own account for a use other than housing. Many commercial property companies (foncières) fall within this exemption, which deprives them neither of the direct action against the builders' ten-year insurers nor of the liability action against the builders themselves.
Where a structural damage policy exists, the timetable for handling the claim is strict: sixty days at most from receipt of the claim notification to give notice of the position on the principle of cover, ninety days at most from that same receipt to make an offer of compensation, fifteen days for payment in the event of acceptance. An additional period, based exclusively on technical considerations and reasoned, may be proposed at the same time as the agreement on principle, up to one hundred and thirty-five days and subject to the express acceptance of the insured. Where those periods are not complied with, or where the offer is manifestly insufficient, the insured may, after notifying the insurer, incur the necessary expenditure, the compensation then being increased by operation of law by interest equal to twice the legal interest rate. On the claim notification and the sanction for the insurer's silence, see our analysis of the time limits for calling on structural damage insurance.
A last point on timing, too often discovered during the expert investigation: Article L. 114-1 of the French Insurance Code subjects actions arising from the insurance contract to a limitation period of two years from the event giving rise to them, that period running, in the event of a claim, only from the day the persons concerned became aware of it if they prove that they were unaware of it until then. Two years therefore run against the insured while the expert investigation is under way.
Summary proceedings for an expert investigation before any trial: exclusive jurisdiction of the place where the building is situated
Once the defects have been identified, the investigative measure is the first decision to be taken. Article 145 of the French Code of Civil Procedure allows the court to order, at the request of any interested party, on application or in summary proceedings (référé), the investigative measures that are legally admissible if there is a legitimate reason to preserve or establish, before any trial, the evidence of facts on which the outcome of a dispute may depend.
Decree No. 2025-619 of 8 July 2025, which entered into force on 1 September 2025 for proceedings brought from that date, added two paragraphs. The court with territorial jurisdiction is in principle, at the applicant's choice, the one that could hear the case on the merits or the one within whose area the measure is to be carried out. But, by way of derogation, where the investigative measure concerns a building, the court of the place where the building is situated has sole jurisdiction. In construction summary proceedings for an expert investigation, the applicant therefore no longer has an option: the summons is brought before the court of the place where the building is situated. Bringing the matter before another court exposes the applicant to a plea of lack of jurisdiction and to a loss of several months.
Whom to summon
The identity of the defendants conditions the enforceability of the report against them. Depending on the configuration, the following must be targeted:
- persons deemed to be builders within the meaning of Article 1792-1, namely the architect, the contractor, the technician or any other person bound to the project owner by a contract for the hire of work, the seller after completion of a work that he or she built or had built, and the agent performing a task comparable to that of a hirer of work
- subcontractors, covered by Article 1792-4-2
- the manufacturer of the work, of the part of the work or of the item of equipment designed and produced to meet precise requirements determined in advance, jointly and severally liable under Article 1792-4, as well as the importer and the person who presented the product as his or her own work by putting his or her name or trademark on it
- the insurers, structural damage and ten-year, whose certificates are attached to quotes and invoices pursuant to Article L. 243-2
Interruption and suspension: not to be confused
Article 2241 of the Civil Code provides that a claim brought before a court, even in summary proceedings, interrupts the limitation period as well as the period for forfeiture, including where it is brought before a court lacking jurisdiction. Article 2239 provides that limitation is suspended where the judge grants an application for an investigative measure made before any trial, the period starting to run again for a duration which may not be less than six months from the day the measure was carried out.
Caution is required as to the application of those texts to the ten-year period. Article 1792-4-1 is drafted in terms of discharge from liability after ten years, whereas Article 1792-4-3 speaks of limitation. The characterisation of the period in Article 1792-4-1 and the applicability of Articles 2239 and 2241 to it are debated questions, settled by case law and not by the texts. The only safe course is never to let the ten-year deadline draw near in reliance on a presumed suspensive effect, and to bring the action on the merits in good time.
Contract clauses do not neutralise tacit acceptance
Works contracts frequently contain a clause under which acceptance can result only from the signature of an adversarial report. Article 1792-5 of the Civil Code deems unwritten any clause whose purpose is either to exclude or limit the liability provided for in Articles 1792, 1792-1 and 1792-2, or to exclude the warranties provided for in Articles 1792-3 and 1792-6 or limit their scope, or to remove or limit the joint and several liability provided for in Article 1792-4. A stipulation that would, by way of form, end up depriving the project owner of warranties that are matters of public policy runs up against that text. The exact scope of this reasoning, and the relationship between contractual freedom as to the arrangements for acceptance and the mandatory nature of the warranties, are matters for case law and must be checked case by case.
Conclusion: fix the date rather than endure it
Tacit acceptance is not a favour granted to a negligent project owner; it is a field of evidence on which the builder and its insurer often arrive better prepared than the investor. A party that has taken possession, paid the balance and filed the papers finds itself, three years later, arguing a date it never wrote down, against opponents who hold its transfer order. Our position is clear: on an asset under renovation, acceptance must be organised as a legal act, not recorded after the event as a fact.
Three practical reflexes. Before taking possession, have a report drawn up by a commissaire de justice and notify any reservation in writing, even if no report of acceptance is signed. Before transferring the balance, check that the 5% retention has been deposited or that a bank guarantee has been provided, and make payment conditional on the clearing of reservations. As soon as the first significant defect appears, have the date of acceptance reconstructed through analysis of the documents, then bring summary proceedings for an expert investigation before the court of the place where the building is situated, which has had sole jurisdiction since 1 September 2025, joining all the builders, subcontractors, manufacturers and insurers concerned. An expert investigation that is enforceable against everyone is worth more than a perfect report obtained against a single defendant.
Frequently asked questions
Is tacit acceptance possible if no report has ever been signed? Yes. Article 1792-6 of the Civil Code expressly provides only for acceptance by agreement and acceptance by the court, pronounced on an adversarial basis, but the case law of the 3rd Civil Chamber of the Cour de cassation accepts that acceptance may result from an unequivocal intention on the part of the project owner to accept the work. That intention is usually inferred from actual taking of possession and full payment of the price. The absence of a report therefore does not prevent the warranties from being triggered, but it shifts the debate onto the evidence of the date.
Which date should be adopted when taking of possession and payment of the balance are several months apart? No text settles this question. The date is fixed by the judge on the basis of the evidence produced, which turns the starting point of the ten-year warranty into an evidential issue. A dated file must therefore be built up, with handover of the keys, the tenant's entry inventory, connection of utilities, works instalment, transfer order and contemporaneous written exchanges. The builder will generally argue for the earliest date, and so will the insurer.
Does full payment of the balance mean losing the benefit of the warranties for apparent defective workmanship? It does not mean losing the benefit of ten-year liability, which covers damage meeting the conditions of Article 1792. However, in the absence of a report, no reservation is formalised, which weakens the project owner's position on defects visible on the day possession was taken. Article 1792-6 then opens the route of written notification for defects revealed after acceptance, which becomes the central tool of the first year.
Does the 5% retention prevent tacit acceptance? No. Law No. 71-584 of 16 July 1971 authorises a retention of no more than 5 per cent of the instalments paid, intended to satisfy, where applicable, the reservations made at acceptance, with deposit in the hands of a depositary or a personal and joint guarantee from a financial institution. It secures performance of the works; it does not suspend acceptance. Conversely, paying the entire balance without applying a retention is one of the strongest indications of tacit acceptance.
Before which court should an application for an expert investigation into defective workmanship be brought? Since Decree No. 2025-619 of 8 July 2025, applicable to proceedings brought from 1 September 2025, Article 145 of the French Code of Civil Procedure states that, where the investigative measure concerns a building, the court of the place where the building is situated has sole jurisdiction. The choice offered by the second paragraph between the court on the merits and the court of the place of execution does not apply in property matters. A wrongly directed application exposes the applicant to a plea of lack of jurisdiction.
Must a property company take out structural damage insurance? Not necessarily. Article L. 242-1 of the French Insurance Code removes the obligation for public-law legal entities and for legal entities carrying on an activity whose scale exceeds the thresholds referred to in the last paragraph of Article L. 111-6, where they have construction work carried out on their own account for a use other than housing. The check must be made operation by operation, distinguishing according to the intended use of the units. In the absence of a structural damage policy, the action is concentrated on the builders and their ten-year insurers.
Do summary proceedings for an expert investigation interrupt the ten-year period of the ten-year warranty? Article 2241 of the Civil Code provides that a claim brought before a court, even in summary proceedings, interrupts the limitation period as well as the period for forfeiture, and Article 2239 suspends limitation where the judge grants an investigative measure before any trial, the period resuming for a duration which may not be less than six months from the day the measure was carried out. The application of those mechanisms to the period in Article 1792-4-1, which is drafted in terms of discharge from liability, is a debated question settled by case law. It is therefore inadvisable to let the ten-year deadline draw near in reliance on a presumed suspensive effect.
The simulator below tells you, from the date of acceptance of the works, which guarantee covers your defect and until when you can act.
Quatre questions suffisent à situer votre position, le délai qui vous reste et ce qu'il faut vérifier en priorité. Vous décidez ensuite si vous en parlez au cabinet.
Décrire ma situationDefects that appeared after handover?
One-year completion warranty, two-year warranty, ten-year liability: which one protects you depends on the nature of the defect and the date of handover.