The delivery of a unit sold off plan (vente en l'état futur d'achèvement, VEFA) is decided in a few hours on site, then in a few weeks of decisions whose irreversible nature the investor rarely appreciates. The report (procès-verbal) is signed, the balance is called, the developer promises to deal with the reservations, and the matter drags on until the day the time limit for acting has expired. Yet the combination of Article 1642-1 of the French Civil Code and Article 1648, paragraph 2, of the same code confines the action for apparent defects within a one-year strict time bar (forclusion) whose starting point is not delivery, contrary to what is often written. This guide deals with VEFA non-conformity from the angle of the decision timetable: what can be demanded on the day the unit is made available, what can be placed in escrow, which warranties can be called upon and at what point proceedings for an expert appraisal in summary proceedings (référé-expertise) become the only useful step before the time bar takes effect.
Completion, acceptance, delivery: three separate dates, three legal effects
The first analytical error is to treat these three notions as a single event. They are not, and the whole timetable depends on the distinction.
Completion within the meaning of Article R. 261-1 of the French Construction and Housing Code (CCH)
Completion is a technical threshold. The building is deemed complete when the works have been carried out and the items of equipment essential to the use of the building that is the subject of the contract, in accordance with its intended purpose, have been installed. The text adds a point that is decisive for the purchaser: in assessing completion, non-conformities with the provisions of the contract are not taken into account where they are not substantial, nor are defective workmanship items that do not make the works unfit for their use.
In other words, a building can be legally complete while showing departures from the descriptive specification (notice descriptive). Article R. 261-1 moreover expressly rules out any extensive reading of that finding:
The finding of completion does not in itself amount to acknowledgement of conformity with the provisions of the contract, nor to a waiver of the rights that the purchaser holds under Article 1642-1 of the Civil Code, reproduced in Article L. 261-5 of this Code, and under Article L. 242-1 of the Insurance Code.
Acceptance of the works
Article 1601-3 of the Civil Code provides that the seller retains the powers of the client (maître de l'ouvrage) until acceptance of the works. Acceptance (réception) is, under Article 1792-6, the act by which the client declares that it accepts the work with or without reservations, whether by agreement or by court decision, and in any event given on an adversarial basis. It therefore takes place between the seller and the contractors, in the absence of the purchaser. It is nonetheless the date that fixes the starting point of the statutory construction warranties.
Delivery
Delivery is the physical handing over of the unit to the purchaser. It is not acceptance. It makes the balance payable under Article R. 261-14 CCH and, combined with acceptance, it starts the countdown to the seller's discharge under Article 1642-1. An investor who reasons "one year from the handing over of the keys" is wrong in both directions: he may believe he is time-barred when he is not, or believe he is within time when the period began earlier.
What Article 1642-1 allows the purchaser to demand: apparent construction defects and non-conformities
Article 1642-1 of the Civil Code, reproduced in Article L. 261-5 CCH, is the central provision at delivery:
The seller of a building to be constructed cannot be discharged, either before acceptance of the works or before the expiry of a period of one month after the purchaser takes possession, from construction defects or non-conformities that are then apparent. There shall be no ground for rescission of the contract or reduction of the price if the seller undertakes to carry out repairs.
Two points deserve emphasis, because they are regularly misreported.
First, the text covers non-conformities, and not only construction defects. This extension results from Article 109 of Law No. 2009-323 of 25 March 2009: before that reform, the article referred only to "apparent construction defects". Earlier commentaries, still plentiful, send apparent non-conformity back to the general law of sale alone. That presentation is no longer accurate. The gap between the thing delivered and the provisions of the contract, a feature of the descriptive specification replaced by another, an item of equipment that is missing, a layout different from that of the annexed plan, falls within the scope of Article 1642-1 where it is apparent.
Second, the seller has a means of avoiding the heaviest sanctions: there is no ground for rescission of the contract or for a reduction of the price if the seller undertakes to carry out repairs. The investor who hopes for a price reduction on a unit delivered non-conforming must factor this into his negotiating strategy: the developer's undertaking to carry out repairs closes the route of a price reduction. The useful lever then shifts to the actual performance of the repairs, their timetable, and compensation for separate losses.
The classification of a defect as "apparent" on the day of delivery, and the evidential weight of the report and of the reservations entered in it, are not defined by any text. They are matters for the courts to assess. This uncertainty calls for a simple rule of conduct: everything that is perceptible must be put in writing.
VEFA delivery and reservations: the discipline of the report
The delivery report (procès-verbal de livraison) is the key document of any later file. Its drafting follows a few practical requirements that every informed investor imposes on his representative.
- Describe the defect, not its remedy: "floor covering different from that provided for in the annexed descriptive specification" rather than "floor to be redone".
- Locate each reservation precisely, room by room, and link it to the contractual provision or plan from which it departs.
- Distinguish contractual non-conformities (departure from the contract and its annexes) from defective workmanship (faulty execution), because the legal bases and the available warranties differ.
- Have the common parts recorded where the unit depends on them for its use, in coordination with the property manager (syndic) and the co-ownership council.
- Be assisted by a construction professional where the economic stake justifies it, in particular for commercial units, technical equipment and announced performance levels.
A generic handwritten note such as "subject to all non-conformities" does not have the value of an inventory. Conversely, a signature without reservations does not in itself amount to a waiver: Article L. 261-16 CCH deems unwritten any clause contrary to Articles L. 261-11 to L. 261-15 CCH and to Articles 1642-1 and 1646-1 of the Civil Code. Advance waiver clauses inserted in certain deeds run up against that provision. It remains the case that the exact scope of a given clause must be assessed on a case-by-case basis.
Escrow of the VEFA balance (consignation): the text, and what it does not say
Article R. 261-14 CCH sets out the staged payment of the price (35% on completion of the foundations, 70% when the building is made watertight, 95% on completion of the building) and then states the rule applicable to the balance:
The balance is payable when the unit is made available to the purchaser; however, it may be placed in escrow in the event of a dispute as to conformity with the provisions of the contract.
The escrow of the VEFA balance is therefore a right under the text, but a narrowly conditioned right and one deliberately left with little detail. Three observations follow.
The condition is a dispute as to conformity with the provisions of the contract. It is not the mere existence of finishing reservations: it is a documented dispute concerning the gap between the work delivered and the contract. Hence the importance of how the report is drafted, since it is the basis of that dispute.
The text sets no percentage. The balance referred to in R. 261-14 is what remains after the 95% payable on completion. Market practice is to place that remainder in escrow, but the amount follows from the contractual staging, not from a rule specific to escrow.
The text does not designate an escrow holder, does not organise any procedure and does not make the release of the funds conditional on the lifting of the reservations. Escrow with the notary or an agreed third party is a matter of contractual practice. A purchaser who simply keeps the funds in his own account is not placing them in escrow: he exposes himself to the late-payment penalty that the contract may provide for, within the limit of 1% per month set by the same article.
Do not transpose the regime of the individual house construction contract
The most frequent confusion consists in importing into VEFA the mechanism of Article R. 231-7 II CCH. That text, specific to the individual house construction contract with supply of plan, provides that where reservations are made, a sum not exceeding 5% of the agreed price is, until the reservations are lifted, placed in escrow with an escrow holder accepted by both parties or, failing that, appointed by the president of the judicial court (tribunal judiciaire). Neither that cap expressed as a percentage of the agreed price, nor the link with the lifting of reservations, nor the judicial appointment of the escrow holder features in the VEFA regime. Relying on R. 231-7 against a developer in a sale off plan file weakens the position of the creditor of proper completion rather than strengthening it.
The countdown: seller's discharge and the time bar of Article 1648
This is where most files are lost.
Article 1642-1 fixes the date on which the seller may be discharged: it cannot occur either before acceptance of the works or before the expiry of a period of one month after the purchaser takes possession. The discharge date is therefore the later of those two dates.
Article 1648, paragraph 2, draws the procedural consequence:
In the case provided for by Article 1642-1, the action must be brought, on pain of being time-barred, within the year following the date on which the seller may be discharged from apparent defects or non-conformities.
Three practical points. First, the period is not "one year from delivery": it runs from the discharge date, itself determined by Article 1642-1. In the usual configuration, where acceptance precedes taking possession, this amounts to one year from the expiry of the month following possession. But where acceptance comes later, or is disputed, the discharge date shifts, and the calculation must be redone with the documents in hand. The investor must therefore obtain from the seller the date of acceptance and the acceptance report, a document he does not receive spontaneously.
Next, this is a time bar and not a limitation period (prescription). Article 2220 of the Civil Code specifies that time bars are not, unless the law provides otherwise, governed by the title devoted to extinctive limitation. The grounds of suspension under the general law therefore do not apply to it automatically.
Finally, the two-year period of Article 1648, paragraph 1, concerns the action arising from latent defects, running from discovery of the defect. It is not the period applicable to the situation of Article 1642-1. The two paragraphs are regularly confused; the error costs an inadmissibility objection.
Post-acceptance warranties: who owes what, and from when
The completion warranty
Article 1792-6 places the completion warranty (garantie de parfait achèvement) on the contractor, in favour of the client, for a period of one year from acceptance. It extends to the remedying of all defects notified by the client, either by reservations recorded in the acceptance report or by written notification for those revealed afterwards. Where there is no agreement on the time for repairs or where they are not carried out, the works may, after a formal notice (mise en demeure) that has remained without effect, be carried out at the expense and risk of the defaulting contractor. The warranty does not extend to works needed to remedy the effects of normal wear or use.
A nuance is called for, one that is often glossed over. Article 1646-1 of the Civil Code, reproduced in Article L. 261-6 CCH, transfers to the purchaser the obligations by which the builders are bound under Articles 1792, 1792-1, 1792-2 and 1792-3. It does not mention Article 1792-6. To state without qualification that the VEFA purchaser "benefits from the seller's completion warranty" on the basis of 1646-1 is therefore not tenable on the present state of the texts. Two relationships must be distinguished: on the one hand the completion warranty, owed by the contractor to the client from acceptance; on the other the warranty against apparent defects and non-conformities under Article 1642-1, owed by the seller to the purchaser from delivery. The extent of the purchaser's rights under the first is a matter for case law and must be examined file by file, as must his standing to act directly against the contractors or their insurers. The regime of this warranty and the repairs it allows the client to impose are set out in our article on the completion warranty under Article 1792-6.
Transferred warranties and their starting points
Article 1792-3 sets a warranty of proper functioning of equipment items for a minimum period of two years from its acceptance. Article 1792-4-1 discharges builders from the liabilities under Articles 1792 to 1792-2 after ten years from acceptance of the works. Article 1792-4-3 provides that other liability actions against builders and their subcontractors are subject to a ten-year limitation period from acceptance. In all three cases the starting point is acceptance, not delivery. Between acceptance and delivery, several months can pass on a large residential scheme: the purchaser who does not know the acceptance date does not know how much time he really has.
Property damage insurance (assurance dommages-ouvrage)
Article L. 242-1 of the Insurance Code requires that, before the site opens, insurance be taken out guaranteeing payment of the full cost of repair works for damage of the kind for which builders are liable under Article 1792 of the Civil Code. The investor must take two limits into account.
The policy covers only damage of a ten-year nature. A contractual non-conformity falls outside its scope. Calling on the property damage insurance for a departure from the descriptive specification leads to a refusal of cover and a loss of time.
The cover takes effect after expiry of the completion warranty period, except in two cases referred to in the text: before acceptance, after a formal notice that has remained without effect, where the works contract is terminated for non-performance by the contractor; after acceptance, after a formal notice that has remained without effect, where the contractor has not performed its obligations. The formal notice is therefore a step in the timetable, not a courtesy formality.
The claim-handling periods must be monitored: sixty days at most to notify the decision on whether the guarantees are engaged, ninety days at most to submit an offer of compensation, fifteen days for payment after acceptance, and an additional period for the preparation of the offer, which requires the insured's express acceptance and may not exceed one hundred and thirty-five days. Where the insurer fails to comply with one of those periods or makes a manifestly insufficient offer, the insured may, after notifying it, incur the expenses necessary for the repair, the compensation then being increased by operation of law by interest equal to twice the legal rate. On the engagement of this insurance and the penalty for the insurer's silence, see our analysis of the periods under the property damage insurance.
Expert appraisal in summary proceedings: Article 145 of the Code of Civil Procedure (CPC), the step that holds the timetable
When negotiations stall, the measure of inquiry before any trial becomes the central tool again. Article 145 of the Code of Civil Procedure allows the ordering of legally admissible measures of inquiry where there is a legitimate reason to preserve or establish, before any trial, evidence of facts on which the outcome of a dispute may depend, at the request of any interested party, on application or in summary proceedings.
Territorial jurisdiction has changed since 1 September 2025
Decree No. 2025-619 of 8 July 2025 added two paragraphs to Article 145, which came into force on 1 September 2025 and apply only to proceedings begun from that date. The court with territorial jurisdiction is, at the claimant's choice, the one likely to hear the case on the merits or the one within whose area the measure of inquiry is to be carried out. But, by derogation from the second paragraph, where the measure of inquiry relates to a building, the court of the place where the building is situated has sole jurisdiction.
The consequence is direct for an investor whose registered office, adviser or jurisdiction clause points to Paris while the scheme is located in the provinces: jurisdiction is exclusive, the choice has gone. A summons issued before the wrong court loses weeks, at a point in the timetable when they count.
The effect on the time bar
Article 2241 of the Civil Code states that a claim brought before the courts, even in summary proceedings, interrupts the limitation period as well as the time bar, including where it is brought before a court lacking jurisdiction or where the originating document is annulled by reason of a procedural defect. It is the only text in the file that expressly refers to the time bar, and the link with the period under Article 1648, paragraph 2, therefore rests on it.
Article 2239, which provides for suspension where the judge grants a request for a measure of inquiry made before any trial, then for the period to resume for a duration that may not be less than six months from the carrying out of the measure, refers in terms only to "limitation". Read with Article 2220, it does not allow one to assert that an order for an expert appraisal in summary proceedings suspends the time bar of Article 1648. The prudent position, and the only one defensible before a judge, is to treat the summons in summary proceedings as an interrupting act within the meaning of Article 2241, to monitor the time bar deadline independently of the progress of the expert's operations, and not to wait for the filing of the report before bringing the action on the merits. The exact scope of the interrupting effect, in particular as regards builders not summoned in the summary proceedings, is a matter for case law and should be secured by a wide joinder of parties from the outset.
Seller in difficulty: what the financial completion guarantee covers, and what it does not
The question arises acutely in a market where developer failures have multiplied. Article L. 261-10-1 CCH, in the wording resulting from Article 75 of Law No. 2018-1021 of 23 November 2018, specifies that the financial completion guarantee may be called upon by the purchaser in the event of the seller's financial default, characterised by a lack of the funds necessary to complete the building. The guarantor may have an ad hoc administrator appointed by order on application, vested with the powers of the client, tasked with having the works necessary for completion carried out and empowered to give acceptance within the meaning of Article 1792-6. Where its guarantee is called upon, the guarantor alone is entitled to require the purchaser to pay the balance of the sale price, even if the seller is subject to proceedings under Book VI of the Commercial Code.
The limit is just as clear. Under Article R. 261-24 CCH, the guarantee ends on completion of the building as defined in Article R. 261-1, completion being evidenced by a certificate delivered to the seller in three original copies. Since completion does not take account of non-substantial non-conformities or of defective workmanship that does not make the works unusable, the financial completion guarantee has lapsed before the delivery reservations have been lifted. It is therefore not security for the proper performance of the repairs. Faced with a weakened developer, the purchaser must look for leverage elsewhere: escrow of the balance on the basis of R. 261-14, joinder of the builders and their insurers, and a proof of claim where appropriate. The mechanism of the guarantee, from its engagement to its termination, is dealt with separately in our article on the financial completion guarantee in VEFA.
The decision timetable, in sequence
The useful sequence is built backwards from the time bar of Article 1648, paragraph 2.
- Before delivery: obtain the descriptive specification, the contractual plans, and the amendments and variations; identify the items substituted during the works.
- On the day of delivery: a written and located inventory of non-conformities and defective workmanship in the report; keeping a signed copy; taking dated photographs.
- In the following days: written notification to the seller of the dispute as to conformity with the provisions of the contract; putting the escrow of the balance in place on the contractual terms; written request for the acceptance report and its date.
- Within the month following possession: additional reservations in writing for defects revealed by use, before the discharge under Article 1642-1 can take effect.
- In the following months: a detailed formal notice to the seller with a time for performance; monitoring of the repair undertakings; calculation of the time bar date from the discharge date.
- At the latest several weeks before the deadline: summons for an expert appraisal in summary proceedings on the basis of Article 145 CPC before the court of the place of the building, joining the seller, the contractors concerned, the project manager (maître d'œuvre) and the insurers identified.
- During the expert appraisal: independent monitoring of the time bar and bringing the proceedings on the merits without waiting for the filing of the report.
Conclusion
Litigation over non-conformity in VEFA is won or lost in the first four weeks, then on a single date: the one on which the seller may be discharged within the meaning of Article 1642-1, which governs the one-year time bar of Article 1648, paragraph 2. Everything else, the quality of the reservations, the escrow, the formal notice, the joinder of the builders, has effect only if that date is known and met. The opposite reflex, waiting for the developer's promises of repair and then for the filing of an expert report, leads to files that are technically sound and procedurally extinguished.
Three practical recommendations. Demand in writing, from delivery, the acceptance report and its date: without it, no calculation of time limits is reliable. Base any escrow on Article R. 261-14 CCH and on a documented dispute as to conformity, without transposing the regime of the individual house construction contract. And, from the moment the seller first seriously refuses, set an internal deadline for summons in summary proceedings for an expert appraisal before the court of the place of the building, fixed several weeks before the time bar and not on its eve.
Frequently asked questions
Does the one-year time bar in VEFA run from the handing over of the keys?
No. Article 1648, paragraph 2, of the Civil Code requires the action to be brought, on pain of being time-barred, within the year following the date on which the seller may be discharged from apparent defects or non-conformities. That date is fixed by Article 1642-1: the seller cannot be discharged either before acceptance of the works or before the expiry of a period of one month after the purchaser takes possession. The later of those two dates must therefore be taken, then one year counted. The acceptance date must be obtained from the seller to make the calculation secure.
Can a purchaser place the balance of the price in escrow if he made reservations at delivery?
Article R. 261-14 CCH provides that the balance is payable when the unit is made available to the purchaser, but that it may be placed in escrow in the event of a dispute as to conformity with the provisions of the contract. The condition laid down is a dispute as to conformity, and not the mere existence of finishing reservations. The text designates neither an escrow holder, nor a procedure, nor a percentage: those terms are a matter for the contract and practice. Keeping the funds without actual escrow exposes the purchaser to the late-payment penalty, the rate of which may not exceed 1% per month under the same article.
Does the 5% held in escrow until the reservations are lifted apply in VEFA?
That mechanism appears in Article R. 231-7 II CCH, specific to the individual house construction contract with supply of plan. It provides that, where there are reservations, a sum not exceeding 5% of the agreed price is, until the reservations are lifted, placed in escrow with an escrow holder accepted by both parties or, failing that, appointed by the president of the judicial court. The VEFA regime of Article R. 261-14 CCH takes over neither that cap, nor the link with the lifting of reservations, nor the judicial appointment. The transposition has no basis in law.
Does the VEFA purchaser benefit from the completion warranty?
Article 1792-6 of the Civil Code places the completion warranty on the contractor in favour of the client, for one year from acceptance, for defects recorded in the acceptance report or notified in writing afterwards. Article 1646-1, which transfers to the purchaser the warranties borne by builders, refers only to Articles 1792, 1792-1, 1792-2 and 1792-3: it does not mention Article 1792-6. The extent of the purchaser's rights under this warranty is therefore a matter for case law. As against the seller, the purchaser's own basis remains Article 1642-1 for apparent defects and non-conformities.
Before which court should an expert appraisal in summary proceedings concerning a building be brought?
Since Decree No. 2025-619 of 8 July 2025, which came into force on 1 September 2025 and applies only to proceedings begun from that date, Article 145 of the Code of Civil Procedure provides for jurisdiction at the claimant's choice between the court likely to hear the case on the merits and that of the place where the measure is to be carried out. But, by derogation, where the measure of inquiry relates to a building, the court of the place where the building is situated has sole jurisdiction. The option is therefore closed in property matters.
Does a court-ordered expert appraisal protect against the time bar?
Article 2241 of the Civil Code provides that a claim brought before the courts, even in summary proceedings, interrupts the limitation period as well as the time bar, including before a court lacking jurisdiction. A summons for an expert appraisal in summary proceedings is therefore an interrupting act. By contrast, Article 2239, which governs suspension where a measure of inquiry is ordered before any trial, refers in terms only to limitation, and Article 2220 specifies that time bars are not governed by the title devoted to extinctive limitation unless otherwise provided. It is therefore imprudent to count on a suspension of the period under Article 1648 during the expert's operations: the action on the merits must be brought before the deadline.
Does property damage insurance cover a non-conformity with the descriptive specification?
No. Article L. 242-1 of the Insurance Code guarantees payment of repair works for damage of the kind for which builders are liable under Article 1792 of the Civil Code, that is, damage of a ten-year nature. A departure from the contractual provisions falls outside that scope. The policy moreover takes effect after expiry of the completion warranty period, subject to the two cases of formal notice that has remained without effect referred to in the text.
Quatre questions suffisent à situer votre position, le délai qui vous reste et ce qu'il faut vérifier en priorité. Vous décidez ensuite si vous en parlez au cabinet.
Décrire ma situationDefects that appeared after handover?
One-year completion warranty, two-year warranty, ten-year liability: which one protects you depends on the nature of the defect and the date of handover.