Environmental authorisation: the examination timetable and litigation risk that govern the closing of an industrial or logistics asset

A fund that signs a promise to sell (promesse) on a 60,000 m² warehouse or on an industrial site being converted generally reasons in two stages: the price, then the date on which the asset becomes available. The environmental authorisation governs both. It fixes the moment at which the asset becomes operable, it determines how long a third party can still seek its annulment before the administrative court, and it conditions the validity of the rental assumption on which the valuation rests. Since Law No. 2023-973 of 23 October 2023, known as the Green Industry Law, and its implementing decrees, then Decree No. 2024-423 of 10 May 2024 on litigation, the timetable has been substantially rewritten: two examination phases instead of three, a third-party appeal period reduced to two months, and powers of the court exercised under a binding duty (compétence liée). This guide reconstructs that timetable step by step and draws from it the conditions precedent, the deliverables and the protections to negotiate before signing.

The environmental authorisation as a determinant of operability, not a mere formality

An environmental due diligence focused solely on soil pollution is incomplete. For a logistics asset or an industrial asset, three distinct questions arise, which have neither the same timetable nor the same risk bearer.

The first concerns the title: does the installation hold an environmental authorisation, a registration or a declaration that effectively covers the activities carried on and those planned by the purchaser? The second concerns the stability of the title: has the third-party appeal period for the environmental authorisation been exhausted, and what is the residual risk of annulment or of a stay of proceedings? The third concerns the liabilities: who bears the securing and remediation of the site on cessation of activity, and what certificates have been produced?

These three questions are answered by specific documents, not by statements from the seller. A seller who produces neither the record of display at the town hall nor the dated screen capture of the prefecture's publication does not allow the date of exhaustion to be calculated: the litigation risk remains open, and it is the purchaser who bears it after closing.

The real starting point of the timetable: filing, completeness, case-by-case review

The examination period does not run from filing. Article R. 181-16 of the French Environmental Code provides that the prefect (préfet) issues proof of filing on receipt of the application but that, if the file does not contain sufficient elements for it to be examined and for the consultations to take place, the prefect invites the applicant to complete or regularise it within a reasonable period which the prefect sets. Article L. 181-9 places the examination after it has been found complete and regular by the administrative authority.

The second turning point, often underestimated in transaction schedules: where the prefect refers the project for case-by-case review within fifteen days of the issue of proof of filing, the file can be regarded as complete and regular only once the prefect has received the decision not to require an environmental assessment. And if the authority responsible for the case-by-case review decides that the project requires an environmental assessment, the applicant files a new application for authorisation including the impact study. In other words, the clock starts again from zero.

Upstream, the available tools have been reduced. Article L. 181-5, in the version resulting from Law No. 2023-175 of 10 March 2023, now mentions only the mandatory referral to the competent authority for case-by-case review where the project is subject to it, the option of seeking information from the competent administrative authority in order to prepare the file, and the request for an opinion on the scope and level of detail of the information to be provided in the impact study provided for in Article L. 122-1-2. Points 2° and 3° of the article are repealed. Advising a project promoter today to secure its timetable by means of a project certificate is an error of positive law.

The environmental authorisation examination period therefore cannot be modelled on an overall statutory duration: no text sets one. The reduction target announced during the work on the Green Industry Law is a public policy objective, not an enforceable rule. A closing timetable built on an average duration, without reservation as to completeness and case-by-case review, is a false timetable.

The examination and consultation phase: the durations that matter for the schedule

Since the Green Industry Law, the examination takes place in only two phases: an examination and consultation phase, then a decision phase (Article L. 181-9). This scheme applies to applications filed from 22 October 2024, pursuant to Decree No. 2024-742 of 6 July 2024; earlier applications continue to be examined under the former three-stage procedure. For a pending file taken over in the course of an acquisition, the first check therefore concerns the filing date: it determines the applicable procedural regime, and therefore the reliability of the back-schedule provided by the seller.

Article L. 181-10-1, in the version currently in force resulting from Law No. 2026-796 of 18 August 2026, organises a public consultation run in parallel with the administrative consultations. The milestones to be entered in the schedule are as follows:

  • on receipt of the file, referral to the president of the administrative court with a view to the appointment of an investigating commissioner (commissaire enquêteur) or an investigation panel, with a substitute;
  • as soon as the file is found complete and regular and the investigating commissioner has been appointed, organisation of the consultation, unless the application is rejected early;
  • duration of the consultation of three months or, where the opinion of the environmental authority is required, one month more than the period allowed to that authority to give its opinion;
  • public opening meeting with the participation of the applicant within fifteen days of the start of the consultation;
  • public closing meeting, with the participation of the applicant, in the last fifteen days of the consultation;
  • report and reasoned conclusions of the investigating commissioner within three weeks of the end of the public consultation.

Receipt of this report and of these reasoned conclusions, or the expiry of the three-week period, ends the examination and consultation phase and opens the decision phase. This point of articulation is the pivot of the timetable: it turns an uncertain deadline into a calculable one.

Two points deserve particular attention on the investor side. First, the answers given by the applicant no later than at the closing meeting are deemed to form part of the application file, as are any consequential changes to the project, provided that they do not alter its overall nature: the conduct of the consultation is therefore an act that structures the title, not a communication formality. Second, Article L. 181-9 allows the administration to reject the application during the examination and consultation phase where the authorisation cannot be granted on the basis of the file or of the project, in particular where the environmental authorisation or the planning permission appears manifestly incapable of being issued having regard to the land use defined by the planning document in force at the time of the examination, unless a revision, amendment or compatibility amendment procedure having the effect of allowing it to be issued has been started. For a logistics project in a constrained zone, coordination with the procedure for amending the local urban plan (PLU) becomes a prerequisite, not an adjustment variable.

The conditions for the application over time of the law of 18 August 2026, in particular the fate of pending applications, call for a case-by-case check before a contractual timetable is fixed.

The decision phase: two months, and the extensions to anticipate

Article R. 181-41 sets the rule: the prefect rules on the application for environmental authorisation within two months from the day on which the prefect sends the applicant the report and conclusions of the investigating commissioner, or the summary of the observations and proposals of the public. This period is extended by one month where the opinion of the departmental commission for nature, landscapes and sites (CDNPS) or that of the departmental council for the environment and for health and technological risks (CODERST) is sought. It may be extended by reasoned order of the prefect by up to two months, or for a longer period if the applicant agrees.

Three grounds for suspension are exhaustively listed: the planning procedure referred to in the last paragraph of Article L. 181-9, until the procedure allowing the project to be carried out has been completed; the request for a third-party expert assessment based on Article L. 181-13, from that request until the expert report is produced; and the joint procedure with the award of a mining title.

Two contractual consequences. First, the applicant's agreement to an extension beyond two months is an act over which the purchaser must control the decision: it should be placed on the list of acts subject to prior consultation during the interim period. Second, the request for a third-party expert assessment, which suspends the period without any ceiling stated in the text, justifies a long-stop date clause with a right of withdrawal, and not a simple automatic extension of the completion period.

The warehouse subject to registration: five months, silence meaning refusal, risk of switching procedure

Many logistics assets fall under the ICPE (classified installations) registration regime rather than the authorisation regime. The timetable then changes radically. Under Article R. 512-46-18, unless the prefect has decided that the application will be examined under the rules of the authorisation procedure, the prefect rules within five months of receipt of the complete and regular file. The prefect may extend that period by two months, by reasoned order, in exceptional cases resulting for example from the nature, complexity, location or size of the project. Failing an express decision within those periods, the prefect's silence amounts to a decision of refusal.

Two operational lessons. Negative silence rules out building a condition precedent on tacit obtaining of the title: only an express, notified decision counts as fulfilment. And the prefect's option to examine the application under the authorisation procedure is a genuine timetable risk, since it replaces the five-month period with the cycle of public consultation plus decision phase described above. For a transaction whose delivery date determines a lease already signed with a single tenant, this switch must be treated as an identified contractual event, with express allocation of its cost.

The exact classification of the headings applicable to a warehouse, and the thresholds that distinguish registration from authorisation, fall under the nomenclature of classified installations and must be checked on the site concerned, activity by activity and volume by volume.

Litigation risk: two months, and no longer four

This is the change that has been least well absorbed in market practice. Since Decree No. 2024-423 of 10 May 2024, Article R. 181-50 provides that the decisions referred to in Articles L. 181-12 to L. 181-15-1 may be challenged before the administrative court by third parties with an interest by reason of the drawbacks or dangers for the interests referred to in Article L. 181-3, within two months from display at the town hall under the conditions laid down in point 2° of Article R. 181-44 or from publication of the decision on the prefecture's website provided for in point 4° of the same article.

The period runs from the last formality completed. If display is that last formality, the period runs from the first day of display of the decision.

The applicant or operator has, for its part, two months from the day on which the decision was notified to it. These provisions apply to administrative decisions taken from 1 September 2024: for an authorisation issued earlier, the four-month period of the former wording remains applicable. In a due diligence concerning an asset authorised in 2023, reasoning on the basis of two months is the mirror image of the error of still reasoning on four months for an authorisation of 2025. The same reduction to two months was made, by the same decree, in Article R. 514-3-1 for the ICPE decisions it covers, the period then running from the first day of publication or display.

The documents to require in order to calculate exhaustion

Article R. 181-44 describes the formalities for informing third parties: filing of a copy of the order at the town hall of the municipality where the installation is located, display of an extract at the town hall for a minimum of one month with a record drawn up by the mayor, transmission to each municipal council and to the other local authorities consulted, and publication on the website of the State services in the département for a minimum of four months.

The list of due diligence deliverables follows mechanically: record of display signed by the mayor, dated proof of the prefecture's online publication, and determination of which of the two formalities took place last. Without these documents, the date of exhaustion cannot be demonstrated and the corresponding condition precedent cannot be recorded as satisfied. The question of the starting point where display is irregular is a matter for administrative case law and must be treated as a contingency, not as a certainty. On the drafting of a condition precedent of a building permit free of appeals in a land acquisition, see our analysis devoted to that mechanism.

Notification of the appeal, a procedural lever for the beneficiary

Article L. 181-17 subjects these decisions to full-jurisdiction litigation and requires the author of the appeal, on pain of inadmissibility, to notify the appeal to the author of the decision and to the beneficiary of the decision. Article R. 181-51 specifies the regime: notification must be made by registered letter with acknowledgement of receipt, within fifteen clear days of the filing of the contentious appeal or of the date of dispatch of the administrative appeal. The author of an administrative appeal is also required to notify it to the beneficiary, on pain of the period for a contentious appeal not being extended. The obligation also applies to applications seeking the annulment or variation of a court decision. These provisions apply to appeals relating to environmental authorisations and supplementary orders made from 1 January 2024.

One clarification must be made, because it still circulates the wrong way round: the sentence providing that an administrative appeal extended the period for a contentious appeal by two months has been deleted from Article R. 181-50, as from Article R. 514-3-1. The version in force merely reserves Article L. 411-2 of the Code on relations between the public and the administration. A purchaser can therefore no longer assume as a principle that an informal administrative appeal (recours gracieux) automatically reopens an additional period for third parties.

What the court will do with the appeal: partial annulment and stay of proceedings under a binding duty

Article L. 181-18, in the version resulting from Law No. 2023-175 of 10 March 2023, applicable to disputes begun from its publication, changes the analysis of the residual risk. An administrative court which, having found that the other grounds are unfounded, considers, even after completion of the works, that a defect affects only one phase of the examination or one part of the authorisation, limits the scope of the annulment to that phase or that part and asks the administration to resume the examination at the defective stage. If it considers that a defect causing illegality is capable of being regularised, it stays proceedings until the expiry of the period that it sets. A refusal to grant a request for partial annulment or a stay of proceedings must be reasoned. Where an annulment or stay affects only part of the authorisation, the court determines whether the execution of the unaffected parts should be suspended.

The shift from an option to a binding duty statistically reduces the scenario of outright total annulment. It does not remove it, and it introduces a timetable risk of its own: a stay of proceedings accompanied by a resumption of the examination may immobilise a decision for several months, with a direct effect on a financing plan tied to a commissioning date. The contractual issue is therefore less the destruction of the title than its prolongation.

Finally, Article L. 181-17 gives the beneficiary a defensive weapon: where the right to bring an appeal is exercised in conditions that amount to abusive conduct on the part of the appellant and that cause harm to the beneficiary of the authorisation, the beneficiary may ask, by separate pleading, for the author of the appeal to be ordered to pay damages. The claim may be made for the first time on appeal. In a case of organised local opposition, this claim must be prepared from the first defence pleading, not improvised.

Lapse of the authorisation and its relationship with litigation

Article R. 181-48 provides that the environmental authorisation order ceases to have effect where the project has not been commissioned or carried out either within the period set by the authorisation order or within three years from the day on which the authorisation was notified, except in cases of force majeure or of a justified and accepted request for extension.

That period is suspended until notification to the beneficiary of a decision that has become final where an appeal is brought before the administrative court against the authorisation order or its supplementary orders, of a decision that has become final where an appeal is brought against the project's building permit or the decision of non-objection to a prior declaration, or of a decision that has become irrevocable where an appeal is brought before a court of the ordinary courts based on Article L. 480-13 of the French Town Planning Code.

The correct reading is therefore as follows: litigation does not make the lapse period run, it suspends it. A purchaser taking over a project authorised for more than two years must reconstruct the chronology of appeals precisely in order to determine the balance of the period actually available before commissioning, and provide in the documentation for a seller's statement that there is no undisclosed appeal.

Transfer of the title to the purchaser: declaration, exceptions, partial transfer

The principle laid down by Article R. 181-47 is simple: transfer of the environmental authorisation is the subject of a declaration addressed to the prefect by the new beneficiary, within three months following the transfer, the prefect acknowledging receipt within one month. For a legal entity, the declaration states its name or corporate name, its legal form, the address of its registered office and the capacity of the signatory.

The exceptions must be identified upstream, because they move the formality to before closing. Transfer of the authorisation granted to the installations referred to in Article R. 516-1 is subject to authorisation. For installations falling under Article L. 515-32 other than those in point 3° of Article R. 516-1, the operator informs the prefect before the planned transfer, with evidence of the technical and financial capacities of the new beneficiary, the prefect having a right of objection notified within two months. For certain hydraulic structures and installations using hydraulic energy, the declaration is made in advance. For authorisations falling under point 3° of Article L. 181-1, the declaration is made at the latest two months before the transfer.

A correction is needed here on a practice that is still widespread. Since Decree No. 2024-742 of 6 July 2024, the list in Article R. 516-1 no longer includes installations presenting a risk of soil pollution that are subject to financial guarantees. Only waste storage installations other than inert waste storage installations, quarries, installations on the list provided for in Article L. 515-36 and geological carbon dioxide storage sites are now subject to prefectoral authorisation for a change of operator. To state that every ICPE site subject to financial guarantees requires an authorisation for a change of operator is now incorrect. Where authorisation is required, the prefect's silence for three months amounts to authorisation for installations in points 1° and 2°, and to refusal for those in points 3° and 4°: the asymmetry must be carried over as it stands into the drafting of the condition precedent. The scope of ICPE financial guarantees and the site restoration liability taken over by the purchaser at closing are analysed in our article devoted to that question.

Where a site is divided or only part of a whole is sold, Article L. 181-15-1 opens the way to a partial transfer: the administrative authority issues to each applicant and to the original holder a separate environmental authorisation if it considers that the change is not substantial, that the partial transfer can take place without harming the interests referred to in Articles L. 181-3 and L. 181-4, and that it is possible to identify the measures falling to each. This is a technical prerequisite for any operation to break up a multi-unit industrial asset.

Liabilities: information for the purchaser, cessation of activity, third-party applicant

Article L. 514-20 requires, where an installation subject to authorisation or registration has been operated on a plot of land, that the seller inform the buyer in writing and also inform the buyer, to the extent known to the seller, of the significant dangers or drawbacks resulting from the operation. If the seller is the operator, the seller states in writing whether its activity involved the handling or storage of chemical or radioactive substances. The deed of sale certifies that this formality has been completed. Failing that, and if a pollution found renders the land unfit for the purpose specified in the contract, the buyer has, within two years of discovery of the pollution, the choice of seeking rescission of the sale or recovery of part of the price; the buyer may also seek remediation of the site at the seller's expense, where the cost of that remediation does not appear disproportionate to the sale price.

For land located in a soil information sector, Article L. 125-7 adds a separate obligation, which also covers lease contracts and opens, as the case may be, rescission of the contract, recovery of part of the price, a rent reduction or remediation within the meaning of Article L. 556-1 A.

On cessation of activity, Article L. 512-6-1 requires the operator to have certified, by a firm certified in the field of polluted sites and soils or having equivalent skills, the implementation of the securing measures, the adequacy of the measures proposed for remediation of the site, and then the implementation of those measures. These three successive certificates are the reference deliverables of a brownfield acquisition. The catch-up arrangement open for cessations notified to the administration before 1 June 2022 could be used until 1 January 2026: at the date of writing, that window is closed. The chronology of the cessation of activity of a classified installation and the determination of future use are dealt with separately in our article devoted to restoration liability.

Finally, Article L. 512-21, in the version resulting from the law of 23 October 2023, usefully extends the third-party applicant mechanism for conversion operations. The substitution request may be made from notification of the cessation of activity, and even in anticipation of a future cessation, with the operator's agreement; it may cover remediation according to the intended use and, now, all or part of the securing measures. The third-party applicant must have sufficient technical capacity and financial guarantees covering the carrying out of the works. A decisive point in the allocation of risk: if the third-party applicant defaults and the financial guarantees cannot be implemented, the last operator remains responsible for securing the installation.

What the purchaser must lock down before signing

The clauses below stem from contractual practice and not from a text: they are negotiated, they are not presumed.

  • A condition precedent of obtaining an express, notified decision, and not an implied decision, in particular for a registration file where silence amounts to refusal.
  • A condition precedent of exhaustion of appeals, whose fulfilment is recorded on documents: record of display, proof of prefectoral publication, certificate of no appeal, taking into account the two-month period for decisions taken from 1 September 2024 and four months for earlier decisions.
  • A clause on the conduct of the examination during the interim period: prohibition on the seller accepting an extension of the decision period beyond two months without the purchaser's written agreement, and immediate notification of any request for a third-party expert assessment or of any switch to the authorisation procedure.
  • An obligation to cooperate on the transfer of the title, with filing of the declaration under Article R. 181-47 or of the authorisation application under Article R. 516-1 depending on the applicable regime, and a contractual timetable aligned with the corresponding prefectoral periods.
  • A seller's statement that there is no undisclosed appeal, whether administrative or contentious, and on the status of the lapse period under Article R. 181-48 taking account of the suspensions that have occurred.
  • Delivery of the certificates under Article L. 512-6-1 for any site that has been the subject of a cessation of activity, and express mention in the deed of the information provided for in Articles L. 514-20 and, where applicable, L. 125-7.

One last point affects the valuation: Article R. 181-46 treats as substantial a change that constitutes an extension requiring a new environmental assessment under II of Article R. 122-2, that reaches quantitative thresholds and criteria set by ministerial order, or that is likely to cause significant dangers and drawbacks for the interests referred to in Article L. 181-3. Issue of a new authorisation is then subject to the same formalities as the initial authorisation, and therefore to a new full cycle of consultation and decision. Other notable changes are brought to the prefect's attention before they are carried out. A business plan that includes an extension of units, a change in the nature of the products stored or the addition of a battery charging activity must therefore provide for an administrative timetable, not only capex.

Conclusion

The environmental authorisation is not to be treated as a document in a file but as an enforceable timetable, each milestone of which can now be identified: completeness and case-by-case review, a three-month consultation with opening and closing meetings, the investigating commissioner's report within three weeks, a prefectoral decision within two months which may be extended, then two months for third-party appeals from the last publicity formality. The reduction of the appeal period to two months and the court's binding duty as regards partial annulment and stay of proceedings shift the risk: outright annulment becomes less likely, and prolongation becomes the central scenario. It is this prolongation, and not the destruction of the title, that must be provided for in the price and in the debt.

Before any signature, have an independent adviser reconstruct the complete administrative chronology of the asset, document by document: date of filing of the application, express decision and its date, record of display, prefectoral publication, balance of the lapse period, applicable transfer regime. As long as these six dates are not documented, the closing date proposed by the seller is only an assumption.

Frequently asked questions

What is the third-party appeal period against an environmental authorisation today?

Two months. Article R. 181-50 of the French Environmental Code, in the version resulting from Decree No. 2024-423 of 10 May 2024, gives third parties with an interest by reason of the drawbacks or dangers for the interests referred to in Article L. 181-3 a period of two months running from the last formality completed between display at the town hall provided for in point 2° of Article R. 181-44 and publication on the prefecture's website provided for in point 4° of the same article. If display is that last formality, the period runs from the first day of display. These provisions apply to administrative decisions taken from 1 September 2024: for an authorisation issued before that date, the four-month period of the former wording remains applicable.

Does an informal administrative appeal still extend the period for a contentious appeal?

The sentence that expressly provided for this two-month extension has been deleted from Article R. 181-50, as from Article R. 514-3-1 for the other ICPE decisions. The version in force merely reserves Article L. 411-2 of the Code on relations between the public and the administration. In addition, the author of an administrative appeal must notify it to the beneficiary of the decision, by registered letter with acknowledgement of receipt and within fifteen clear days of its dispatch, on pain of the period for a contentious appeal not being extended. A risk analysis that assumes an automatic extension needs to be revised.

How long does the examination of an environmental authorisation take?

No text sets an overall duration. The Environmental Code sets durations for each sequence: public consultation of three months, or one month more than the period allowed to the environmental authority where its opinion is required; investigating commissioner's report within three weeks of the end of the consultation; prefect's decision within two months of the sending of that report to the applicant, extended by one month where the CODERST or the CDNPS is consulted, and capable of extension by reasoned order of up to two months, or more with the applicant's agreement. To these are added, upstream, the time needed to make the file complete and, where applicable, that of the case-by-case review. The total duration is therefore modelled file by file.

Does a logistics warehouse subject to registration follow the same timetable?

No. Under Article R. 512-46-18, the prefect rules within five months of receipt of the complete and regular file, which may be extended by two months by reasoned order in exceptional cases. The prefect's silence amounts to a decision of refusal, which rules out building a condition precedent on tacit obtaining. Above all, the prefect may decide to examine the application under the rules of the authorisation procedure: this switch must be treated contractually as an identified timetable event.

Does transfer of the authorisation to the purchaser require the prefect's prior agreement?

In principle no: Article R. 181-47 provides for a simple declaration by the new beneficiary to the prefect within three months following the transfer, the prefect acknowledging receipt within one month. Prior prefectoral authorisation is required only for the installations listed in Article R. 516-1, that is, since Decree No. 2024-742 of 6 July 2024, waste storage installations other than inert waste, quarries, installations on the list provided for in Article L. 515-36 and geological carbon dioxide storage sites. Other derogating regimes exist, in particular prior information for certain installations falling under Article L. 515-32 and prior declaration for certain hydraulic structures.

Does a contentious appeal make the lapse period of the authorisation run?

It suspends it. Article R. 181-48 provides that the order ceases to have effect if the project has not been commissioned or carried out within the period set by the order or, failing that, within three years of notification of the authorisation, and that this period is suspended until notification of a decision that has become final where an appeal is brought against the environmental authorisation or its supplementary orders, or against the building permit or the non-objection to a prior declaration, or that has become irrevocable for a judicial appeal based on Article L. 480-13 of the French Town Planning Code. For an asset authorised long ago, the balance of the useful period must be reconstructed from the exact chronology of appeals.

What can the court do when seised of an appeal against an environmental authorisation?

Article L. 181-18, in the version resulting from Law No. 2023-175 of 10 March 2023, requires the court, having found that the other grounds are unfounded and even after completion of the works, to limit the annulment to the phase of the examination or the part of the authorisation tainted by irregularity, and to stay proceedings where a defect causing illegality is capable of being regularised. A refusal to grant a request for partial annulment or a stay must be reasoned. Where there is a partial annulment or stay, the court determines whether the execution of the unaffected parts should be suspended. The beneficiary may also claim, by separate pleading and for the first time on appeal, damages where the appeal amounts to abusive conduct on the part of the appellant and causes the beneficiary harm, on the basis of Article L. 181-17.

The simulator below tells you which planning permission is required, the processing times, the appeal deadlines and how long the permit remains valid.

Votre situation ressemble-t-elle à celle-ci ?

Quatre questions suffisent à situer votre position, le délai qui vous reste et ce qu'il faut vérifier en priorité. Vous décidez ensuite si vous en parlez au cabinet.

Décrire ma situation
Sans engagement – réponse du cabinet sous quarante-huit heures ouvrées.
• Vous êtes concerné ?

A question about your own situation?

The firm assists business owners, investors and private individuals, from upstream advice through to litigation.

generique
environmental-authorisation-timetable-and-litigation-risk-at-closing
Questionnaire
×
Merci, votre demande est bien parvenue au cabinet. Une réponse vous sera adressée sous quarante-huit heures ouvrées.
L’envoi n’a pas abouti. Vous pouvez écrire directement à contact@avocats-gloria.com.

Vos réponses aux questions précédentes sont jointes à votre message. Réponse sous quarante-huit heures ouvrées.

Ces questions ne constituent pas une consultation juridique et ne remplacent pas l’examen de vos pièces. Les informations transmises servent uniquement à répondre à votre demande et ne sont pas cédées à des tiers.

← Question précédente

Gloria Avocats, your trusted legal partner

By email or by telephone, the firm will answer all your questions.

• Contact us