A defect appears in a building delivered three years ago: cracking of a load-bearing wall, water ingress through a flat roof terrace, a heat pump out of service, or simply a floor area smaller than the one promised in the contract. The first question is not "who pays", but "how is this defect classified". The warranty that can be called on, the defendant to be sued, the time limit for acting and the possibility of calling on an insurer all depend on that classification. This guide sets out the classification grid arising from Articles 1792 et seq. of the French Civil Code, the specific regime for defects in off-plan sales (vente en l'état futur d'achèvement, VEFA), and the procedural reflex that conditions everything else: summary proceedings for an expert appraisal (référé-expertise) under Article 145 of the French Code of Civil Procedure, commenced before a forfeiture period (forclusion) takes effect.
Poor workmanship, non-conformity, ten-year defect: three notions, a single legal criterion
It must be said plainly: neither the word "malfaçon" (poor workmanship) nor the expression "contractual non-conformity" appears in Articles 1792 et seq. of the French Civil Code. These categories are tools of legal writing and case law. Positive law reasons on four objective parameters: the seriousness of the damage, the nature of the element affected, whether or not the defect was the subject of a reservation at acceptance, and the date of acceptance. A search for a "definition of malfaçons" in a search engine will therefore never return a statute, but a construction developed by the courts.
Poor workmanship, a defect in carrying out the work to the standards of the building trade
By malfaçon, practice means a defect in the execution of the works measured against good building practice or the applicable technical standards: a badly proportioned render, defective tile layout, waterproofing laid without sufficient upstand, inadequate fixing. Malfaçon is a technical notion, not an autonomous legal category. It opens no warranty by itself: it must be attached to one of the statutory regimes according to its consequences. A malfaçon may remain a mere aesthetic defect, fall within the functioning warranty if it affects an item of equipment, or move into the ten-year field if it renders the work unfit for its purpose.
Contractual non-conformity, a departure from the contract regardless of seriousness
Non-conformity is measured against a different standard: not good building practice, but the contractual stipulation. The work delivered is not the work that was promised. Tiles of a different specification, reduced ceiling height, a technical room moved, the absence of an item of equipment listed in the descriptive specification. The work may be perfectly executed and nevertheless non-conforming. The choice between "malfaçon or non-conformity" is therefore not cosmetic: non-conformity is assessed by item-by-item comparison with the contract, its annexes and the descriptive specification, which means producing these documents from the expert appraisal phase. The exact scope of a non-conformity that causes no unfitness for purpose is a matter for the courts' assessment, not for a statute.
The ten-year defect, the only category defined by statute
Article 1792 of the French Civil Code sets the only textual criterion of seriousness:
Any builder of a work is liable as of right to the owner or purchaser of the work for damage, even resulting from a defect in the ground, which compromises the solidity of the work or which, affecting it in one of its constituent elements or one of its items of equipment, renders it unfit for its purpose. Such liability does not arise if the builder proves that the damage comes from an external cause.
Two alternative limbs, therefore: impairment of solidity, or unfitness for purpose. Liability is as of right, which relieves the claimant of proving fault: it is enough to establish the damage, its connection with the work and its seriousness. The builder is released only by proving an external cause. It is this reversal of the burden of proof that makes ten-year classification the first objective of any claimant's strategy.
Acceptance, the time pivot of the whole scheme
Article 1792-6 defines acceptance (réception) as the act by which the owner of the work declares that it accepts the work with or without reservations. It takes place at the request of the most diligent party, by agreement or by the court, and is in any event, pronounced in the presence of both parties. All warranty periods, completion, functioning, ten-year, run from that date. An owner who does not have a dated and signed acceptance report therefore does not know which time limits can be raised against it. The content of the report and the different forms of acceptance are detailed in our article on acceptance of works and the transfer of risk.
The report also governs the fate of apparent defects. A defect visible on the day of acceptance and not reserved is not covered by the completion warranty, the scope of which the text expressly limits to defects that have been reported. The care taken in drafting reservations is therefore an act of risk management, not a site formality. Tacit acceptance, admitted by case law, is not enshrined in the text: in the absence of a report, its date is the subject of a technical debate that is most often settled in the course of the expert appraisal.
Completion warranty: one year, the contractor, only the defects reported
Article 1792-6 confines the completion warranty (garantie de parfait achèvement) to a period of one year from acceptance and places it on the contractor. Its scope is delimited in two ways:
- it extends to the repair of all defects reported by the owner of the work, either by means of reservations noted in the acceptance report, or by written notification for those revealed after acceptance;
- it does not extend to the works needed to remedy the effects of normal wear or use.
Three operational consequences. First, written notification of defects revealed after acceptance is constitutive of the right: without writing, no completion warranty. Second, the warranty is indifferent to the seriousness of the defect, which makes it the natural vehicle for minor malfaçons and many non-conformities during the first year. Third, the text refers to the contractor, and not to the project manager (maître d'œuvre) or the architect: the action must be directed against the right person.
The text provides its own route to enforcement. The repair periods are set by agreement; failing agreement or in the event of non-performance within the set period, the works may, after a formal notice that has remained unsuccessful, be carried out at the expense and risk of the defaulting contractor. For an institutional landlord or an investor faced with unusable premises, this facility is a lever for speeding things up. It requires a formal notice that is precise and kept on file.
Article 1792-5 deems unwritten any clause excluding or limiting the scope of this warranty, as of those of Articles 1792, 1792-1, 1792-2 and 1792-3, and any clause excluding the joint liability of Article 1792-4. Works contracts that attempt to cap builders' liability run up against this public policy rule.
Functioning warranty: two years minimum, items of equipment
Article 1792-3 provides that the other items of equipment of the work are covered by a functioning warranty (garantie de bon fonctionnement) of a minimum duration of two years from its acceptance. Since the Law of 8 June 2005, the text refers to items of equipment "of the work" and no longer "of the building", which widens its base. Two points matter in practice: the duration is a minimum, which may be extended by contract, and the warranty presupposes an item of equipment that can be separated.
The boundary with the ten-year warranty is drawn by Article 1792-2, which extends the presumption of Article 1792 to damage affecting the solidity of items of equipment, but only where these form an inseparable part of the infrastructure, foundation, framework, enclosure or roofing works. The criterion is statutory and material: an item is inseparable where its removal, dismantling or replacement cannot be carried out without damaging or removing material from that work. The question arises concretely for underfloor heating embedded in the slab, sealed-in joinery, applied cladding. It is for the court-appointed expert to describe the method of removal: the wording of the expert's brief must therefore include this point.
Article 1792-7 excludes from the scope of Articles 1792, 1792-2, 1792-3 and 1792-4 items of equipment, including their accessories, whose exclusive function is to allow a professional activity to be carried on in the work. For an investor in office or logistics property, the exclusion is structuring: process equipment benefits from none of the statutory construction warranties and falls under the general law of contract.
Finally, Article 1792-4 makes the manufacturer of a work, part of a work or an item of equipment designed to meet precise and specified requirements jointly liable for the obligations of Articles 1792, 1792-2 and 1792-3, as is the importer and anyone who affixes their name, brand or any other distinctive sign. This basis usefully widens the circle of solvent debtors.
Ten-year classification: solidity, unfitness for purpose, and the rest
In practice, the claimant has an interest in arguing for ten-year classification whenever the facts allow, for three cumulative reasons: liability as of right, the ten-year period, and the compulsory insurance that goes with it. Classically falling within unfitness for purpose are repeated water ingress making premises unusable, a generalised waterproofing defect, an installation that prevents normal occupation of the premises. Impairment of solidity covers structural defects: foundations, framework, floor slab.
Article 1792-1 designates the persons deemed to be builders: any architect, contractor, technician or other person bound to the owner of the work by a contract for the hire of work; any person who sells, after completion, a work that they built or had built; any person who, although acting as the owner's agent, carries out a mission comparable to that of a party hiring out work. The builder-seller and the developer are therefore in the front line, which is directly relevant to the purchaser of a recently restructured asset.
Defects that do not meet the seriousness criterion of Article 1792 and do not concern an item of equipment within the meaning of Article 1792-3 are not for that reason beyond any action. Practice calls them intermediate damage and deals with them on the ground of contractual liability for proven fault, a construction of case law of which only the time limit is statutory: Article 1792-4-3 provides that apart from the actions governed by Articles 1792-3, 1792-4-1 and 1792-4-2, liability actions against the builders designated in Articles 1792 and 1792-1 and their subcontractors are time-barred after ten years from acceptance of the works. Applying to these defects the five-year limitation period of Article 2224 is a frequent and costly error as to regime.
VEFA: the dual grid of apparent defects and construction warranties
A purchaser in an off-plan sale combines two sets of rights, and confusion between the two explains a large share of procedural failures in VEFA defect cases.
The first set concerns defects apparent on delivery. Article 1642-1 of the French Civil Code, in the wording resulting from Law No. 2009-323 of 25 March 2009 and reproduced in Article L. 261-5 of the French Construction and Housing Code, states that the seller of a building to be constructed cannot be discharged, either before acceptance of the works or before the expiry of a period of one month after the purchaser takes possession, from construction defects or non-conformities then apparent. Since 2009, the text does refer to non-conformities, and not only construction defects: departure from the contract is expressly covered.
The time limit for acting is a forfeiture period, not a limitation period. Article 1648, paragraph 2, requires that, in the case provided for by Article 1642-1, the action must be brought, on pain of forfeiture, within the year following the date on which the seller may be discharged from apparent defects or non-conformities. This one-year forfeiture must never be confused with the two-year period of the first paragraph applicable to latent defects giving rise to rescission. In concrete terms, the purchaser who takes possession and draws up a list of reservations has a short window for action, which closes without any prior formal notice.
The second set concerns construction warranties. Article 1646-1 provides that the seller of a building to be constructed is bound, from acceptance of the works, by the obligations of Articles 1792, 1792-1, 1792-2 and 1792-3, and specifies that these warranties benefit successive owners of the building. Two consequences for an investor: the acquisition of a unit resold by the first purchaser carries with it transfer of the residual statutory warranties, and the date of acceptance of the works, which is not the date of delivery of the unit, must be obtained and checked at the time of the acquisition audit.
Summary proceedings for an expert appraisal under Article 145 CPC: the reflex to trigger before the forfeiture period
The classification of a defect cannot be decreed, it is demonstrated technically. Hence the almost systematic nature of summary proceedings for an expert appraisal under Article 145 of the Code of Civil Procedure (CPC) in construction litigation. The text authorises, if there is a legitimate reason to preserve or establish, before any trial, the evidence of facts on which the outcome of a dispute might depend, the ordering of investigative measures at the request of any interested party, on application or in summary proceedings. On the legitimate reason and the framing of the expert's brief, see our analysis of summary proceedings for an expert appraisal before a property or construction dispute.
Territorial jurisdiction since 1 September 2025
Decree No. 2025-619 of 8 July 2025 added two paragraphs to Article 145, applicable to proceedings commenced from 1 September 2025. The principle is that the claimant chooses between the court likely to hear the case on the merits and the court within whose jurisdiction the measure is to be carried out. But the text adds a mandatory derogation: where the investigative measure concerns a building, the court of the place where the building is located has sole jurisdiction. In construction defect matters, there is therefore no longer any option. A summons served before the court of the developer's or the owner's registered office exposes the claimant to a plea of lack of jurisdiction and to a loss of time which, when a forfeiture deadline is close, is sometimes irreparable.
Effect on time limits: distinguishing interruption and suspension
Two texts, two effects, and a confusion to avoid. Article 2241 of the French Civil Code provides that a claim brought before the courts, even in summary proceedings, interrupts the limitation period as well as the forfeiture period, including where it is brought before a court lacking jurisdiction or where the originating document is annulled by reason of a procedural defect. This is the basis of the protective effect of a summons in summary proceedings for an expert appraisal, and it expressly refers to forfeiture.
Article 2239 produces a distinct effect: limitation is also suspended where the judge grants an application for an investigative measure made before any trial, time starting to run again for a period of not less than six months, from the day on which the measure was carried out. The text refers only to limitation. To extend this suspension without reservation to forfeiture periods, in particular to the one-year forfeiture of Article 1648, paragraph 2, would be an extrapolation. The rule of conduct is simple: do not count on suspension to manage a forfeiture period, and apply to the judge early enough.
Interplay with other summary proceedings and the prior amicable step
Article 835 of the Code of Civil Procedure allows, even where there is a serious dispute, the ordering of the protective or restorative measures required to prevent imminent damage or to put an end to a manifestly unlawful disturbance, and, where the existence of the obligation is not seriously contestable, the granting of an interim payment or an order to perform an obligation to do something. For an asset in operation, combining the application for an expert appraisal with an application for protective measures is often the only way to stop the damage worsening during the months of the expert's work.
As for Article 750-1 of the Code of Civil Procedure, in the wording resulting from Decree No. 2023-357 of 11 May 2023 applicable to proceedings commenced from 1 October 2023, it requires a prior attempt at conciliation, mediation or participatory procedure, on pain of inadmissibility which the judge may raise of his own motion, only for claims seeking payment of a sum not exceeding €5,000, for the actions of Articles R. 211-3-4 and R. 211-3-8 of the French Code of Judicial Organisation, or in matters of abnormal neighbourhood disturbance. The text also provides for an exemption based in particular on manifest urgency. Most construction disputes with significant stakes therefore escape this filter, but the point must be checked file by file.
Time limits and insurers: the computation grid to keep up to date
Article 1792-4-1 discharges any person whose liability may be engaged under Articles 1792 to 1792-4 from the liabilities and warranties weighing on them under Articles 1792 to 1792-2 after ten years from acceptance of the works or, under Article 1792-3, on expiry of the period referred to in that article. Article 1792-4-2 subjects actions against the subcontractor to ten years from acceptance for the damage of Articles 1792 and 1792-2, and to two years for that affecting the items of equipment of Article 1792-3. The subcontractor is not bound by the ten-year warranty, but its exposure is confined within these same time limits.
On the insurance side, Article L. 241-1 of the French Insurance Code requires any person whose ten-year liability may be engaged to be covered by insurance and to prove that cover at the start of any building site. Article L. 242-1 requires the owner of the work, the seller or its agent to take out before the start of the building site a construction damage insurance policy (assurance dommages-ouvrage) guaranteeing, irrespective of any determination of liability, payment of the full cost of the works to repair damage of a ten-year nature. Its time limits are mandatory and are counted to the day:
- 60 days at most from receipt of the claim declaration to notify the insurer's position on the principle of cover;
- 90 days at most from that same receipt to make an offer of indemnity, where appropriate on an interim basis;
- 15 days for payment after the insured accepts the offer;
- a possible additional period in the event of exceptional difficulties, subject to the express acceptance of the insured and capped at 135 days.
Failure to comply with any of these time limits, like a manifestly insufficient offer, entitles the insured, after notifying the insurer, to incur the expenses needed for the repair, the indemnity then being increased as of right by interest equal to twice the legal interest rate. Dommages-ouvrage cover takes effect after expiry of the completion warranty period, except in two cases of formal notice that has remained unsuccessful: termination, before acceptance, of the contract for the hire of work for non-performance by the contractor, and non-performance by the contractor of its obligations after acceptance. The insured's response to the insurer's silence or refusal is dealt with separately in our article on calling on the dommages-ouvrage cover.
Finally, Article L. 124-3 of the French Insurance Code gives the injured third party a right of direct action against the liable party's insurer, an action that remains subject to the two-year limitation period of Article L. 114-1. Since Law No. 2021-1837 of 28 December 2021, this text contains an exception of five years for damage resulting from ground movements following drought-rehydration of soils recognised as a natural disaster, not applicable to contracts in force on the day the law was published.
Which court to apply to
For private works, jurisdiction lies with the tribunal judiciaire, which under Article L. 211-3 of the French Code of Judicial Organisation hears all civil and commercial cases for which jurisdiction is not assigned, by reason of the nature of the claim, to another court. A useful clarification: the list of exclusive jurisdictions in Article R. 211-3-26 refers to "petitory real actions", which does not cover construction defect litigation. The latter falls within general jurisdiction, and not within an exclusive jurisdiction under that list. For the investigative measure, on the other hand, the rule of Article 145, paragraph 3, applies: the court of the place of the building, and that court alone.
Conclusion: classify early, apply early
Construction litigation is rarely lost on the technical merits. It is lost on a classification adopted too late, on a time limit wrongly computed and on an expert appraisal launched after a warranty has expired. Three decisions must be made as soon as the defect is discovered: the exact date of acceptance, the category of warranty targeted in light of the seriousness criterion of Article 1792 and the nature of the element affected, and the list of potential debtors, builders, seller, manufacturer, subcontractors and their insurers. The rest follows.
Our position is clear-cut: where a defect is evolving or its classification is arguable, the summons in summary proceedings for an expert appraisal before the court of the place of the building should be served without waiting for the outcome of amicable exchanges, joining all the identified parties and insurers to the case. Article 2241 attaches to this application an interruptive effect which also applies to forfeiture, and it is precisely this effect that a prolonged negotiation causes to be lost. Before any decision, have an adversarial chronology of the file drawn up: date of acceptance, content of the reservations, dates of written notification of defects, date of taking possession in a VEFA, deadlines under Articles 1792-6, 1792-3, 1792-4-1 and 1648 paragraph 2. This chronology, and not the technical assessment of the defect, determines the window for action actually available.
Frequently asked questions
What is the legal definition of poor workmanship (malfaçon)? There is none in Articles 1792 et seq. of the French Civil Code. Malfaçon is a technical notion, designating a defect in execution measured against good building practice, which the law penalises only once it is attached to a statutory regime: the completion warranty of Article 1792-6 if the defect was reserved or notified in writing within the year following acceptance, the functioning warranty of Article 1792-3 if it affects a separable item of equipment, the ten-year warranty of Article 1792 if it compromises the solidity of the work or renders it unfit for its purpose.
Malfaçon or non-conformity: does the distinction change the time limit for acting? Yes, mainly in a VEFA. For apparent construction defects and non-conformities, Article 1642-1 of the French Civil Code prohibits any discharge of the seller before acceptance and before expiry of a period of one month after taking possession, and Article 1648 paragraph 2 requires action to be brought on pain of forfeiture within the year following that date. Outside this framework, classification mainly governs the warranty that can be called on and the regime of proof, liability under Article 1792 being as of right whereas intermediate damage requires proof of fault.
Does an item of equipment fall under the ten-year warranty or the functioning warranty? The criterion is set by Article 1792-2: the item falls under the ten-year warranty where it forms an inseparable part of the infrastructure, foundation, framework, enclosure or roofing works, that is, where its removal, dismantling or replacement cannot be carried out without damaging or removing material from that work. Failing that, the functioning warranty of Article 1792-3 applies, with a minimum duration of two years from acceptance. Article 1792-7 also excludes items whose exclusive function is to allow a professional activity to be carried on in the work.
Before which court should summary proceedings for an expert appraisal concerning a building be brought? Since Decree No. 2025-619 of 8 July 2025, applicable to proceedings commenced from 1 September 2025, Article 145 of the Code of Civil Procedure provides that, where the investigative measure concerns a building, the court of the place where the building is located has sole jurisdiction. The option between the court on the merits and the court of the place where the measure is carried out, opened by the second paragraph, is therefore set aside in property matters. Applying to another court exposes the claimant to a plea of lack of jurisdiction.
Do summary proceedings for an expert appraisal interrupt the forfeiture period of Article 1648 paragraph 2? Article 2241 of the French Civil Code states that a claim brought before the courts, even in summary proceedings, interrupts the limitation period as well as the forfeiture period, including before a court lacking jurisdiction. Article 2239, which suspends the period where the judge grants an investigative measure before any trial and makes time start to run again for a period of not less than six months after the measure is carried out, refers only to limitation. It is therefore imprudent to count on Article 2239 to manage a forfeiture period: the summons must be served before the deadline.
What is the time limit for acting against a subcontractor? Article 1792-4-2 of the French Civil Code subjects actions against the subcontractor to ten years from acceptance of the works for damage affecting a work or items of equipment referred to in Articles 1792 and 1792-2, and to two years from that same acceptance for damage affecting the items of equipment of Article 1792-3. The subcontractor is not bound by the ten-year warranty, but its liability is confined within these time limits.
What should be done if the dommages-ouvrage insurer does not respond? Article L. 242-1 of the French Insurance Code gives it 60 days from receipt of the claim declaration to notify its position on the principle of cover, 90 days to make an offer of indemnity and 15 days to pay after acceptance. Where any of these time limits is not met or the offer is manifestly insufficient, the insured may, after notifying the insurer, incur the expenses needed for the repair, the indemnity then being increased as of right by interest equal to twice the legal interest rate.
The simulator below tells you, from the date of acceptance of the works, which guarantee covers your defect and until when you can act.
Quatre questions suffisent à situer votre position, le délai qui vous reste et ce qu'il faut vérifier en priorité. Vous décidez ensuite si vous en parlez au cabinet.
Décrire ma situationDefects that appeared after handover?
One-year completion warranty, two-year warranty, ten-year liability: which one protects you depends on the nature of the defect and the date of handover.